Utah Administrative Code (Current through November 1, 2019) |
R315. Environmental Quality, Waste Management and Radiation Control, Waste Management |
R315-310. Permit Requirements for Solid Waste Facilities |
R315-310-1. Applicability |
Latest version.
|
(1) The following solid waste facilities require a permit: (a) New and existing Class I, II, III, IV, V, VI, and coal combustion residual (CCR) Landfills and coal combustion residual surface impoundments; (b) Class I, II, III, IV, V, and VI Landfills that have closed but have not met the requirements of Subsection R315-302-3(7); (c) incinerator facilities that are regulated by Rule R315-306; (d) land treatment disposal facilities that are regulated by Rule R315-307; and (d) waste tire storage facilities. (2) Permits are not required for corrective actions at solid waste facilities performed by the state or in conjunction with the United States Environmental Protection Agency or in conjunction with actions to implement the Comprehensive Environmental Response Compensation and Liability Act of 1980 (CERCLA), or corrective actions taken by others to comply with a state or federal cleanup order. (3) The requirements of Sections R315-310-2 through 12 apply to each existing and new solid waste facility as indicated. (a) The Director may incorporate a compliance schedule for each existing facility to ensure that the owner or operator, or both, of each existing facility meet the requirements of Rule R315-310. (b) The owner or operator, or both, where the owner and operator are not the same person, of each new facility or expansion at an existing solid waste facility, for which a permit is required, shall: (i) apply for a permit according to the requirements of Rule R315-310; (ii) not begin the construction or the expansion of the solid waste facility until a permit has been granted; and (iii) not accept waste at the solid waste facility prior to receiving the approval required by Subsection R315-301-5(1). (4) A landfill may not change from its current class, or subclass, to any other class, or subclass, of landfill except by meeting all requirements for the desired class, or subclass, to include obtaining a new permit from the Director for the desired class, or subclass, of landfill. (5) Any facility that is in operation at the time that a permit is required for the facility by Subsection R315-310-1(a) and has submitted a permit application within six months of the date the facility became subject to the permit requirements of Subsection R315-310-1(a) may continue to operate during the permit review period but must meet all applicable requirements of rules R315-301 through 320 unless an alternative requirement has been approved by the Director. |
R315-310-2. Procedures for Permits |
Latest version.
|
(1) Prospective applicants may request the Director to schedule a pre-application conference to discuss the proposed solid waste facility and application contents before the application is filed. (2) Any owner or operator who intends to operate a facility subject to the permit requirements must apply for a permit with the Director. Two copies of the application, signed by the owner or operator and received by the Director are required before permit review can begin. (3) Applications for a permit must be completed in the format prescribed by the Director. (4) An application for a permit, all reports required by a permit, and other information requested by the Director shall be signed as follows: (a) for a corporation: by a principal executive officer of at least the level of vice-president; (b) for a partnership or sole proprietorship: by a general partner or the proprietor; (c) for a municipality, State, Federal, or other public agency: by either a principal executive officer or ranking elected official; or (d) by a duly authorized representative of the person above, as appropriate. (i) A person is a duly authorized representative only if the authorization is made in writing, to the Director, by a person described in Subsections R315-310-2(4)(a), (b), or (c), as appropriate. (ii) The authorization may specify either a named individual or a position having responsibility for the overall operation of the regulated facility or activity, such as the position of facility manager, director, superintendent, or other position of equivalent responsibility. (iii) If an authorization is no longer accurate and needs to be changed because a different individual or position has responsibility for the overall operation of the facility, a new authorization that meets the requirements of Subsections R315-310-2(4)(d)(i) and (ii) shall be submitted to the Director prior to or together with any report, information, or application to be signed by the authorized representative. (5) Filing Fee and Permit Review Fee. (a) A filing fee, as required by the Annual Appropriations Act, shall accompany the filing of an application for a permit. The review of the application will not begin until the filing fee is received. (b) A review fee, as established by the Annual Appropriations Act, shall be charged at an hourly rate for the review of an application. The review fee shall be billed quarterly and shall be due and payable quarterly. (6) All contents and materials submitted as a permit application shall become part of the approved permit and shall be part of the operating record of the solid waste disposal facility. (7) The owner or operator, or both, of a facility shall apply for renewal of the facility's permit every ten years. |
R315-310-3. General Contents of a Permit Application for a New Facility or a Facility Seeking Expansion |
Latest version.
|
(1) Each permit application for a new facility or a facility seeking expansion shall contain the following: (a) the name and address of the applicant, property owner, and responsible party for the site operation; (b) a general description of the facility accompanied by facility plans and drawings and, except for Class IIIb, IVb, and Class VI Landfills and waste tire storage facilities, unless required by the Director, the facility plans and drawings shall be signed and sealed by a professional engineer registered in the State of Utah; (c) a legal description and proof of ownership, lease agreement, or other mechanism approved by the Director of the proposed site, latitude and longitude map coordinates of the facility's front gate, and maps of the proposed facility site including land use and zoning of the surrounding area; (d) the types of waste to be handled at the facility and area served by the facility; (e) the plan of operation required by Subsection R315-302-2(2); (f) the form used to record weights or volumes of wastes received required by Subsection R315-302-2(3)(a)(i); (g) an inspection schedule and inspection log required by Subsection R315-302-2(5)(a); (h) the closure and post-closure plans required by Section R315-302-3; (i) documentation to show that any waste water treatment facility, such as a run-off or a leachate treatment system, is being reviewed or has been reviewed by the Division of Water Quality; (j) a proposed financial assurance plan that meets the requirements of Rule R315-309; and (k) A historical and archeological identification efforts, which may include an archaeological survey conducted by a person holding a valid license to conduct surveys issued under R694-1. (2) Public Participation Requirements. (a) Each permit application shall provide: (i) the name and address of all owners of property within 1,000 feet of the proposed solid waste facility; and (ii) documentation that a notice of intent to apply for a permit for a solid waste facility has been sent to all property owners identified in Subsection R315-310-3(3)(a)(i). (iii) the Director with the name of the local government with jurisdiction over the site and the mailing address of that local government office. (b) The Director shall send a letter to each person identified in Subsection R315-310-3(3)(a)(i) and (iii) requesting that they reply, in writing, if they desire their name to be placed on an interested party list to receive further public information concerning the proposed facility. (3) Special Requirements for a Commercial Solid Waste Disposal Facility. (a) The permit application for a commercial nonhazardous solid waste disposal facility shall contain the information required by Subsections 19-6-108(9) and (10). (b) Subsequent to the issuance of a solid waste permit by the Director, a commercial nonhazardous solid waste disposal facility shall meet the requirements of Subsection 19-6-108(3)(c) and provide documentation to the Director that the solid waste disposal facility is approved by the local government, the Legislature, and the governor. (c) Construction of the solid waste disposal facility may not begin until the requirements of Subsections R315-310-3(2)(b) are met and approval to begin construction has been granted by the Director. (d) Commercial solid waste disposal facilities solely under contract with a local government within the state to dispose of nonhazardous solid waste generated within the boundaries of the local government are not subject to Subsections R315-310-3(2)(a), (b), and (c). |
R315-310-4. Contents of a Permit Application for a New or Expanded Class I, II, III, IV, V, and VI Landfill Facility as Specified |
Latest version.
|
(1) Each application for a new or expanded landfill shall contain the information required by Section R315-310-3. (2) Each application shall also contain: (a) the following maps shall be included in a permit application for a Class I, II, III, IV, V, and VI Landfill: (i) topographic map of the landfill unit drawn to a scale of 200 feet to the inch containing five foot contour intervals where the relief exceeds 20 feet and two foot contour intervals where the relief is less than 20 feet, showing the boundaries of the landfill unit, ground water monitoring wells, landfill gas monitoring points, and borrow and fill areas; and (ii) the most recent full size U.S. Geological Survey topographic map, 7-1/2 minute series, if printed, or other recent topographic survey of equivalent detail of the area, showing the waste facility boundary, the property boundary, surface drainage channels, existing utilities, and structures within one-fourth mile of the facility site, and the direction of the prevailing winds. (b) a permit application for a Class I, II, IIIa, IVa, and V Landfill shall contain a geohydrological assessment of the facility that addresses: (i) local and regional geology and hydrology, including faults, unstable slopes and subsidence areas on site; (ii) evaluation of bedrock and soil types and properties, including permeability rates; (iii) depths to ground water or aquifers; (iv) direction and flow rate of ground water; (v) quantity, location, and construction of any private and public wells on the site and within 2,000 feet of the facility boundary; (vi) tabulation of all water rights for ground water and surface water on the site and within 2,000 feet of the facility boundary; (vii) identification and description of all surface waters on the site and within one mile of the facility boundary; (viii) background ground and surface water quality assessment and identification of impacts of the existing facility upon ground and surface waters from landfill leachate discharges; (ix) calculation of a site water balance; and (x) conceptual design of a ground water and surface water monitoring system, including proposed installation methods for these devices and where applicable, a vadose zone monitoring plan; (c) a permit application for a Class I, II, IIIa, IVa, and V Landfill shall contain an engineering report, plans, specifications, and calculations that address: (i) how the facility will meet the location standards pursuant to Section R315-302-1 including documentation of any demonstration made with respect to any location standard; (ii) the basis for calculating the facility's life; (iii) cell design to include liner design, cover design, fill methods, elevation of final cover and bottom liner, and equipment requirements and availability; (iv) identification of borrow sources for daily and final cover, and for soil liners; (v) interim and final leachate collection, treatment, and disposal; (vi) ground water monitoring plan that meets the requirements of Rule R315-308; (vii) landfill gas monitoring and control that meets the requirements of Subsection R315-303-3(5); (viii) design and location of run-on and run-off control systems; (ix) closure and post-closure design, construction, maintenance, and land use; and (x) quality control and quality assurance for the construction of any engineered structure or feature, excluding buildings at landfills, at the solid waste disposal facility and for any applicable activity such as ground water monitoring. (d) a permit application for a Class I, II, III, IV, V, and VI Landfill shall contain a closure plan to address: (i) closure schedule; (ii) capacity of the solid waste disposal facility in volume and tonnage; (iii) final inspection by regulatory agencies; and (iv) identification of closure costs including cost calculations and the funding mechanism. (e) a permit application for a Class I, II, III, IV, V, and VI Landfill shall contain a post-closure plan to address, as appropriate for the specific landfill: (i) site monitoring of: (A) landfill gas on a quarterly basis until the conditions of either Subsection R315-302-3(7)(b) or Subsection R315-302-3(7)(c) are met; (B) ground water on a semiannual basis, or other schedule as determined by the Director, until the conditions of either Subsection R315-302-3(7)(b) or Subsection R315-302-3(7)(c) are met; and (C) surface water, if required, on the schedule specified by the Director and until the Director determines that the monitoring of surface water may be discontinued; (ii) inspections of the landfill by the owner or operator: (A) for landfills that are required to monitor landfill gas, and Class II Landfills, on a quarterly basis; and (B) for other landfills that are not required to monitor landfill gas, on a semiannual basis; (iii) maintenance activities to maintain cover and run-on and run-off systems; (iv) identification of post-closure costs including cost calculations and the funding mechanism; (v) changes to record of title as specified by Subsection R315-302-2(6); and (vi) list the name, address, and telephone number of the person or office to contact about the facility during the post-closure period. |
R315-310-5. Contents of a Permit Application for a New or Expanding Class III, IV, or VI Landfill |
Latest version.
|
(1) Each application for a permit for a new Class III, IV, or VI landfill or for a permit to expand an existing Class III, IV, or VI Landfill shall contain the information required in Section R315-310-3. (2) Each application shall also contain an engineering report, plans, specifications, and calculations that address: (a) the information and maps required by Subsections R315-310-4(2)(a)(i) and (ii); (b) the design and location of the run-on and run-off control systems; (c) the information required by Subsections R315-310-4(2)(d) and (e); (d) the area to be served by the facility; and (e) how the facility will meet the requirements of Rule R315-304, for a Class III Landfill, or Rule R315-305, for a Class IV or VI Landfill. (3) Each application for a Class IIIa or Class IVa Landfill permit shall also contain the applicable information required in Subsections R315-310-4(2)(b)and (c). |
R315-310-6. Contents of a Permit Application for a New or Expanding Landtreatment Disposal Facility |
Latest version.
|
(1) Each application for a landtreatment disposal facility permit shall contain the information required in Section R315-310-3. (2) Each application for a permit shall also contain: (a) a geohydrological assessment of the facility site that addresses all of the factors of Subsection R315-310-4(2)(b); (b) engineering report, plans, specifications, and calculations that address: (i) how the proposed facility will meet the location standards pursuant to Section R315-302-1; (ii) how the proposed facility will meet the standards of Rule R315-307; (iii) the basis for calculating the facility's life; (iv) waste analyses and methods to periodically sample and analyze solid waste; (v) design of interim waste storage facilities; (vi) design of run-on and run-off control systems; (vii) a contour map of the active area showing contours to the nearest foot; (viii) a ground water and surface water monitoring program; and (ix) access barriers such as fences, gate, and warning signs. (c) a plan of operation that in addition to the requirements of Section R315-302-2 addresses: (i) operation and maintenance of run-on and run-off control systems; (ii) methods of taking ground water samples and for maintaining ground water monitoring systems; and (iii) methods of applying wastes to meet the requirements of Section R315-307-3. (d) closure plan to address: (i) closure schedule; (ii) capacity of site in volume and tonnage; and (iii) final inspection by regulatory agencies. (e) post-closure plan to address: (i) estimated time period for post-closure activities; (ii) site monitoring of ground water; (iii) changes in record of title; (iv) maintenance activities to maintain cover and run-off system; (v) plans for food-chain crops, if any, being grown on the active areas, after closure; and (vi) identification of final closure costs including cost calculations and the funding mechanism. |
R315-310-7. Contents of a Permit Application for a New or Expanding Incinerator Facility |
Latest version.
|
(1) Each application for a new or expanding incinerator facility permit shall contain the information required in Section R315-310-3. (2) Each application for a permit shall also contain: (a) engineering report, plans, specifications, and calculations that address: (i) the design of the storage and handling facilities on-site for incoming waste as well as fly ash, bottom ash, and any other wastes produced by air or water pollution controls; and (ii) the design of the incinerator or thermal treater, including charging or feeding systems, combustion air systems, combustion or reaction chambers, including heat recovery systems, ash handling systems, and air pollution and water pollution control systems. Instrumentation and monitoring systems design shall also be included. (b) an operational plan that, in addition to the requirements of Section R315-302-2, addresses: (i) cleaning of storage areas as required by Subsection R315-306-2(5); (ii) alternative storage plans for breakdowns as required in Subsection R315-306-2(3); (iii) inspections to insure compliance with state and local air pollution laws and to comply with Subsection R315-302-2(5)(a). The inspection log or summary must be submitted with the application; (iv) how and where the fly ash, bottom ash, and other solid waste will be disposed; and (v) a program for excluding the receipt of hazardous waste equivalent to requirements specified in Subsection R315-303-4(7). (c) documentation to show that air pollution and water pollution control systems are being reviewed or have been reviewed by the Division of Air Quality and the Division of Water Quality. (d) a closure plan to address: (i) closure schedule; (ii) closure costs and a financial assurance mechanism to cover the closure costs; (iii) methods of closure and methods of removing wastes, equipment, and location of final disposal; and (iv) final inspection by regulator agencies. |
R315-310-8. Contents of a Permit Application for a New or Expanding Waste Tire Storage Facility |
Latest version.
|
Each application for a waste tire storage facility permit shall contain the information required in Subsections R315-310-3(1)(a), (b), (c), (f), (g), (h), (k), R315-310-3(2) and Subsection R315-314-3(3). |
R315-310-9. Contents of an Application for a Permit Renewal |
Latest version.
|
The owner or operator, or both, where the owner and operator are not the same person, of each existing facility who intend to have the facility continue to operate, shall apply for a renewal of the permit by submitting the applicable information and application specified in Sections R315-310-3, -4, -5, -6, -7, or -8, as appropriate. Applicable information, that was submitted to the Director as part of a previous permit application, may be copied and included in the permit renewal application so that all required information is contained in one document. The information submitted shall reflect the current operation, monitoring, closure, post-closure, and all other aspects of the facility as currently established at the time of the renewal application submittle. |
R315-310-10. Contents of an Application for a Permit for a Facility in Post-Closure Care |
Latest version.
|
The application for a Post-Closure Care permit shall contain the applicable information required in Section R315-310-3 and documentation as to how the facility will meet the requirements of Section R315-302-3(5) and (6). |
R315-310-11. Permit Transfer |
Latest version.
|
(1) A permit may not be transferred without approval from the Director, nor shall a permit be transferred from one property to another. (2) The new owner or operator shall submit to the Director: (a) A revised permit application no later than 60 days prior to the scheduled change and (b) A written agreement containing a specific date for transfer of permit responsibility between the current and new permittees. (3) The new permittee shall: (a) assume permit requirements and all financial responsibility; (b) provide adequate documentation that the permittee has or shall have ownership or control of the facility for which the transfer of permit has been requested; (c) demonstrate adequate knowledge and ability to operate the facility in accordance with the permit conditions; and (d) demonstrate adequate financial assurance as required in the permit and R315-309 for the operation of the facility. (4) When a transfer of ownership or operational control occurs, the old owner or operator shall comply with the requirements of Rule R315-309 until the new owner or operator has demonstrated that it is complying with the requirements of that rule. (5) An application for permit transfer may be denied if the Director finds that the applicant has: (a) knowingly misrepresented a material fact in the application; (b) refused or failed to disclose any information requested by the Director; (c) exhibited a history of willful disregard of any state or federal environmental law; or (d) had any permit revoked or permanently suspended for cause under any state or federal environmental law. |
R315-310-12. Contents of a Permit Application for a New or Expanding Coal Combustion Residual Landfill and Coal Combustion Residual Surface Impoundment |
Latest version.
|
Each application for a coal combustion residual landfill and coal combustion residual surface impoundment permit shall contain the information required in Subsections R315-310-3(1)(a) and (k), and Section R315-319. |