Utah Administrative Code (Current through November 1, 2019) |
R23. Administrative Services, Facilities Construction and Management |
R23-5. Contingency Funds |
R23-5-8. Funding of Project Reserve
Latest version.
-
(1) After all major construction contracts for a project have been awarded, and after setting aside adequate reserves for any remaining construction work which was not included in the construction contracts, any remaining balance of Appropriated Funds in the construction budget shall be transferred to the Project Reserve.
(2) Upon completion of the project, any residual balance of Appropriated Funds in any budget category shall be transferred to the Project Reserve; however, if the residual balance is the result of a reduction in a contract balance which had previously been funded from the Statewide Contingency Reserve, the residual balance shall be transferred instead to the Statewide Contingency Reserve.