Utah Administrative Code (Current through November 1, 2019) |
R23. Administrative Services, Facilities Construction and Management |
R23-5. Contingency Funds |
R23-5-9. Use of Project Reserve
Latest version.
-
The Division may utilize the Project Reserve only for the award of construction contracts which exceed the available construction budget. This may only be done after a review of other options to bring the cost within available funding and a determination that this action is necessary in order to meet the intent of the project.