R746-312-16. Public Utility Maps, Records and Reports  


Latest version.
  • (1) Each public utility shall maintain current records of interconnection customer generating facilities showing size, location, generator type, and date of interconnection authorization.

    (2) By July 1 of each year, the public utility shall submit to the commission an annual report with the following summary information for the previous calendar year:

    (a) the total number of generating facilities approved and their associated attributes including resource type, generating capacity, and zip code of generating facility location,

    (b) the total rated generating capacity of generating facilities by resource type,

    (c) for net metering interconnections, the total net excess generation kilowatt-hours received from interconnection customers by month,

    (d) for net metering interconnections, the total amount of excess generation credits in kilowatt hours, and their associated dollar value that have expired at the end of each annualized billing period.