  • (1) Permits being renewed are subject to the same procedural requirements, including those for public participation, affected State and EPA review, that apply to initial permit issuance.

    (2) Permit expiration terminates the source's right to operate unless a timely and complete renewal application has been submitted consistent with R307-415-7b and R307-415-5a(1)(c).

    (3) If a timely and complete renewal application is submitted consistent with R307-415-7b and R307-415-5a(1)(c)and the director fails to issue or deny the renewal permit before the end of the term of the previous permit, then all of the terms and conditions of the permit, including the permit shield, shall remain in effect until renewal or denial.