R23-26-7. Payment of Claim  


Latest version.
  • (1) When a stand alone component of a Claim has received a final determination, and is no longer subject to review or appeal, that amount shall be paid in accordance with the payment provisions of the contract or judicial order.

    (2) When the entire Claim has received a final determination, and is no longer subject to review or appeal, the full amount shall be paid within fourteen (14) days of the date of the final determination unless the work or services has not been completed, in which case the amount shall be paid in accordance with the payment provisions of the contract to the point that the work or services is completed.

    (3) The final determination date is the earlier of the date upon which the claimant accepted the settlement in writing with an executed customary release document and waived its rights of appeal, or the expiration of the appeal period.

    (4) Any final determination where the Division is to pay additional monies to the Contractor shall not be delayed by any appeal or request for judicial review by another party brought into the process by the Division as being liable to the Division.

    (5) Notwithstanding any other provision of this rule, payment of all or part of a Claim is subject to any set-off , claims or counterclaims of the Division.

    (6) Payment to the Contractor for a Subcontractor issue (Claim) deemed filed by the Contractor, shall be paid by the Contractor to the Subcontractor in accordance with the contract between the Contractor and the Subcontractor.

    (7) The execution of a customary release document related to any payment may be required as a condition of making the payment.