Utah Administrative Code (Current through November 1, 2019) |
R645. Natural Resources, Oil, Gas and Mining; Coal |
R645-100. Administrative: Introduction |
R645-100-400. Applicability
-
410. Except as provided under R645-100-420, the R645 Rules apply to all coal exploration and coal mining and reclamation operations, except:
411. The extraction of coal by a landowner for his or her own noncommercial use from land owned or leased by him or her. Noncommercial use does not include the extraction of coal by one unit of an integrated company or other business or nonprofit entity which uses the coal in its own manufacturing or power plants;
412. The extraction of 250 tons of coal or less by a person conducting coal mining and reclamation operations. A person who intends to remove more than 250 tons is not exempted;
413. The extraction of coal as an incidental part of federal, state or local government-financed highway or other construction in accordance with R645-102.
414. The extraction of coal incidental to the extraction of other minerals where coal does not exceed 16-2/3 percent of the mineral tonnage removed for commercial use or sale in accordance with R645-106; or
415. Coal exploration on lands subject to the requirements of 43 CFR Parts 3480-3487.
420. Existing Structure Exemption. Each structure used in connection with or to facilitate coal exploration or coal mining and reclamation operations will comply with the performance standards and design requirements of R645-301 and R645-302, except that:
421. An existing structure which meets the performance standards but does not meet the design requirements of R645-301 and R645-302 may be exempted from meeting those design requirements by the Division. The Division may grant this exemption only as part of the permit application process after obtaining the information required by R645-301-526.110 through R645-301-526.115.4 and after making the findings required by R645-300-130.
422. If the performance standard of the MC Rules (Interim Program Rules) is at least as stringent as the comparable performance standard of the R645 Rules, an existing structure which meets the performance standards of the MC Rules may be exempted by the Division from meeting the design requirements of the R645 Rules. The Division may grant this exemption only as part of the permit application process after obtaining the information required by R645-301-526.110 through R645-301-526.115.4 and after making the findings required by R645-300-130.
423. An existing structure which meets a performance standard of the MC Rules which is less stringent than the comparable performance standard in the R645 Rules will be modified or reconstructed to meet the design standard of the R645 Rules pursuant to a compliance plan approved by the Division only as part of the permit application as required in R645-301-526.110 through R645-301-526.115.4 and according to the findings required by R645-300-130.
424. An existing structure which does not meet the performance standards of the MC Rules and which the applicant proposes to use, in connection with or to facilitate the coal exploration or coal mining and reclamation operation, will be modified or reconstructed to meet the performance design standards of R645-301 and R645-302 prior to issuance of the permit.
430. The exemptions provided in paragraphs R645-100-421 and R645-100-422 will not apply to:
431. The requirements for existing and new coal mine waste disposal facilities; and
432. The requirements to restore the approximate original contour of the land.
440. Regulatory Determination of Exemption. The Division may, on its own initiative, and will, within a reasonable time of a request from any person who intends to conduct coal mining and reclamation operations, make a written determination whether the operation is exempt under R645-100-400. The Division will give reasonable notice of the request to interested persons. Prior to the time a determination is made, any person may submit, and the Division will consider, any written information relevant to the determination. A person requesting that an activity be declared exempt will have the burden of establishing the exemption. If a written determination of exemption is reversed through subsequent administrative or judicial action, any person who, in good faith, has made a complete and accurate request for an exemption, and relied upon the determination, will not be cited for violations which occurred prior to the date of the reversal.
450. Termination of Jurisdiction.
451. The Division may terminate its jurisdiction under the regulatory program over the reclaimed site of a completed coal mining and reclamation operation, or increment thereof, when:
451.100. The Division determines in writing that under the initial program all requirements imposed under the MC rules have been successfully completed; or
451.200. The Division determines in writing that under the permanent program all requirements imposed under the applicable regulatory program have been successfully completed or, where a performance bond was required, the Division has made a final decision in accordance with the State program to release the performance bond fully.
452. Following a termination under R645-100-451, the Division will reassert jurisdiction under the regulatory program over a site if it is demonstrated that the bond release or written determination referred to under R645-100-451 was based upon fraud, collusion, or misrepresentation of a material fact.