R315-319-94. Groundwater Monitoring and Corrective Action - Detection Monitoring Program  


Latest version.
  •   (a) The owner or operator of a CCR unit shall conduct detection monitoring at all groundwater monitoring wells consistent with Section R315-319-94. At a minimum, a detection monitoring program shall include groundwater monitoring for all constituents listed in appendix III to Rule R315-319.

      (b) Except as provided in Subsection R315-319-94(d), the monitoring frequency for the constituents listed in appendix III to Rule R315-319 shall be at least semiannual during the active life of the CCR unit and the post-closure period. For existing CCR landfills and existing CCR surface impoundments, a minimum of eight independent samples from each background and downgradient well shall be collected and analyzed for the constituents listed in appendix III and IV to Rule R315-319 no later than October 17, 2017. For new CCR landfills, new CCR surface impoundments, and all lateral expansions of CCR units, a minimum of eight independent samples for each background well shall be collected and analyzed for the constituents listed in appendices III and IV to Rule R315-319 during the first six months of sampling.

      (c) The number of samples collected and analyzed for each background well and downgradient well during subsequent semiannual sampling events shall be consistent with Subsection R315-319-93(e), and shall account for any unique characteristics of the site, but shall be at least one sample from each background and downgradient well.

      (d) The owner or operator of a CCR unit may demonstrate the need for an alternative monitoring frequency for repeated sampling and analysis for constituents listed in appendix III to Rule R315-319 during the active life and the post-closure care period based on the availability of groundwater. This demonstration shall be submitted and approved by the Director. If there is not adequate groundwater flow to sample wells semiannually, the alternative frequency shall be no less than annual. The need to vary monitoring frequency shall be evaluated on a site-specific basis. The demonstration shall be supported by, at a minimum, the information specified in Subsections R315-319-94(d)(1) and (2).

      (1) Information documenting that the need for less frequent sampling. The alternative frequency shall be based on consideration of the following factors:

      (i) Lithology of the aquifer and unsaturated zone;

      (ii) Hydraulic conductivity of the aquifer and unsaturated zone; and

      (iii) Groundwater flow rates.

      (2) Information documenting that the alternative frequency will be no less effective in ensuring that any leakage from the CCR unit will be discovered within a timeframe that will not materially delay establishment of an assessment monitoring program.

      (3) The owner or operator shall obtain a certification from a qualified professional engineer stating that the demonstration for an alternative groundwater sampling and analysis frequency meets the requirements of Section R315-319-94. The owner or operator shall include the demonstration providing the basis for the alternative monitoring frequency and the certification by a qualified professional engineer in the annual groundwater monitoring and corrective action report required by Subsection R315-319-90(e).

      (e) If the owner or operator of the CCR unit determines, pursuant to Subsection R315-319-93(h) that there is a statistically significant increase over background levels for one or more of the constituents listed in appendix III to Rule R315-319 at any monitoring well at the waste boundary specified under Subsection R315-319-91(a)(2), the owner or operator shall:

      (1) Except as provided for in Subsection R315-319-94(e)(2), within 90 days of detecting a statistically significant increase over background levels for any constituent, establish an assessment monitoring program meeting the requirements of Subsection R315-319-95.

      (2) The owner or operator may demonstrate that a source other than the CCR unit caused the statistically significant increase over background levels for a constituent or that the statistically significant increase resulted from error in sampling, analysis, statistical evaluation, or natural variation in groundwater quality. The owner or operator shall complete the written demonstration within 90 days of detecting a statistically significant increase over background levels to include obtaining a certification from a qualified professional engineer verifying the accuracy of the information in the report. If a successful demonstration is completed within the 90-day period, the owner or operator of the CCR unit may continue with a detection monitoring program under Section R315-319-94. If a successful demonstration is not completed within the 90-day period, the owner or operator of the CCR unit shall initiate an assessment monitoring program as required under Subsection R315-319-95. The owner or operator shall also include the demonstration in the annual groundwater monitoring and corrective action report required by Subsection R315-319-90(e), in addition to the certification by a qualified professional engineer.

      (3) The owner or operator of a CCR unit shall prepare a notification stating that an assessment monitoring program has been established. The owner or operator has completed the notification when the notification is placed in the facility's operating record as required by Subsection R315-319-105(h)(5).

      (f) The owner or operator of the CCR unit shall comply with the recordkeeping requirements specified in Subsection R315-319-105(h), the notification requirements specified in Subsection R315-319-106(h), and the Internet requirements specified in Subsection R315-319-107(h).