R309-705-4. Financial Assistance Methods  


Latest version.
  • (1) Eligible Activities of the SRF.

    Funds within the SRF may be used for loans and other authorized forms of financial assistance. Funds may be used for the construction of publicly or privately owned works or facilities, or any work that is an eligible project cost as defined by 73-10c-2 of the Utah Code or as allowed by 42 U.S.C.A. 300f et seq. Those costs incurred subsequent to the submission of a funding application to the Board and prior to the execution of a financial assistance agreement and which meet the above criteria are eligible for reimbursement from the proceeds of the financial assistance agreement.

    (2) Types of Financial Assistance Available for Eligible Water Systems.

    (a) Loans.

    To qualify for "negative interest" or "principal forgiveness", the system must qualify as a "disadvantaged community" as defined in section 3 of this rule. Upon application, the Board will make a case by case determination whether the system is a "disadvantaged community". To be eligible to be considered as a disadvantaged community, the system must meet the definition provided in section 3 of this rule. Additionally, the Board will consider the type of community served by the system, the economic condition of the community, the population characteristics of those served by the system, factors relating to costs, charges and operation of the water system, and other such information as the Board determines relevant to making the decision to recognize the system as a "disadvantaged community".

    (i) Hardship Grant Assessment.

    The assessment will be calculated based on the procedures and formulas shown in section 6 of this rule.

    (ii) Repayment.

    Annual repayments of principal, interest, fees and/or Hardship Grant Assessment generally commence not later than one year after project completion. Project completion shall be defined as the date the funded project is capable of operation and a notice of "beneficial occupancy" is given to the general contractor. Where a project has been phased or segmented, the repayment requirement applies to the completion of individual phases or segments.

    The loan must be fully amortized not later than 20 years after project completion or not later than 30 years after project completion if the community served by the water system is determined to be a disadvantaged community. The yearly amount of the principal repayment is set at the discretion of the Board.

    (iii) Principal Forgiveness.

    Eligible water systems meeting the definition of "disadvantaged community" may qualify for financial assistance in the form of forgiveness of the principal loan amount. Terms for principal forgiveness will be determined by Board resolution.

    Eligible applicants for "principal forgiveness" financial assistance will be considered by the Board on a case-by-case basis. The Board will consider the type of community served by the system, the economic condition of the community, the population characteristics of those served by the system, factors relating to costs, charges and operation of the water system, and such other information as the Board determines relevant to making the decision to recognize the system as a disadvantaged community.

    (iv) Negative Interest Rate.

    Eligible water systems meeting the definition of "disadvantaged community" may qualify for financial assistance in the form of a loan with a negative interest rate, as determined by Board resolution.

    Eligible applicants for "negative interest" financial assistance will be considered by the Board on a case-by-case basis. The Board will consider the type of community served by the system, the economic condition of the community, the population characteristics of those served by the system, factors relating to costs, charges and operation of the water system, and such other information as the Board determines relevant to making the decision to recognize the system as a disadvantaged community.

    (v) Dedicated Repayment Source and Security.

    Loan recipients must establish one or more dedicated sources of revenue for repayment of the loan. As a condition of financial assistance, the applicant must demonstrate a revenue source and security, as required by the Board.

    (b) Refinancing Existing Debt Obligations.

    The Board may use funds from the SRF to buy or refinance municipal, inter-municipal or interstate agencies, where the initial debt was incurred and construction started after July 1, 1993. Refinanced projects must comply with the requirements imposed by the Safe Drinking Water Act(SDWA) as though they were projects receiving initial financing from the SRF.

    (c) Credit Enhancement Agreements and Interest Buy-Down Agreements.

    The Board will determine whether a project's funding may receive all or part of a loan, credit enhancement agreement or interest buy-down agreement. To provide security for project obligations, the Board may agree to purchase project obligations of applicants, or make loans to the applicants. The Board may also consider making loans to the applicants to pay the cost of obtaining letters of credit from various financial institutions, municipal bond insurance, or other forms of insurance or security for project obligations. The Board may also consider other methods of assistance to applicants to properly enhance the marketability of or security for project obligations.

    Interest buy-down agreements may consist of any of the following:

    (i) A financing agreement between the Board and applicant whereby a specified sum is loaned to the applicant. The loaned funds shall be placed in a trust account, which shall be used exclusively to reduce the cost of financing for the project.

    (ii) A financing agreement between the Board and the applicant whereby the proceeds of bonds purchased by the Board is combined with proceeds from publicly issued bonds to finance the project. The rate of interest on bonds purchased by the Board may carry an interest rate lower than the interest rate on the publicly issued bonds, which when blended together will provide a reduced annual debt service for the project.

    (iii) Any other legal method of financing which reduces the annual payment amount on publicly issued bonds. The financing alternative chosen should be the one most economically advantageous for the State and the applicant.

    (d) Technical Assistance.

    The Board may establish a fund (or account) into which the proceeds of an annual fee on loans will be placed. These funds will be used to finance technical assistance for eligible water systems.

    This fund will provide low interest loans for technical assistance and any other eligible purpose as defined by Section 1452 of the Safe Drinking Water Act (SDWA) Amendments of 1996 to water systems that are eligible for Federal SRF loans. Repayment of these loans may be waived in whole or in part (grant funds) by the Board whether or not the borrower is disadvantaged.

    (i) The Board may establish a fee to be assessed against loans authorized under the Federal SRF Loan Program. The revenue generated by this fee will be placed in a new fund called the "SRF Technical Assistance Fund".

    (ii) The amount will be assessed as a percentage of the Principal Balance of the loan on an annual basis, the same as the annual interest and hardship grant assessment are assessed. The borrower will pay the fee annually when paying the principal and interest or hardship grant assessments.

    (iii) The Board may set / change the amount of the fee from time to time as they determine meets the needs of the program.

    (iv) This fee will be part of the "effective rate" calculated for the loan using Table 2, R309-705-6. This fee may be charged in lieu of or in addition to the interest rate or hardship grant assessment, but in no case will the total of the technical assistance fee, the interest rate, and hardship grant assessment exceed the "effective rate".

    (v) The proceeds of the fund will be used as defined above or as modified by the Board in compliance with Section 1452 of the federal SDWA Amendments of 1996.

    (3) Ineligible Projects.

    Projects which are ineligible for financial assistance include:

    (a) Any project for a water system in significant non-compliance, as measured by a "not approved" (R309-400) rating, unless the project will resolve all outstanding issues causing the non-compliance.

    (b) Any project where the Board determines that the applicant lacks the technical, managerial, or financial capability to achieve or maintain SDWA compliance, unless the Board determines that the financial assistance will allow or cause the system to maintain long-term capability to stay in compliance.

    (c) Any project meant to finance the expansion of a drinking water system to supply or attract future population growth. Eligible projects, however, can be designed and funded at a level which will serve the population that a system expects to serve over the useful life of the facility.

    (d) Projects which are specifically prohibited from eligibility by Federal guidelines. These include the following:

    (i) Dams, or rehabilitation of dams;

    (ii) Water rights, unless the water rights are owned by a system that is being purchased through consolidation as part of a capacity development strategy;

    (iii) Reservoirs, except for finished water reservoirs and those reservoirs that are part of the treatment process and are located on the property where the treatment facility is located;

    (iv) Laboratory fees for monitoring;

    (v) Operation and maintenance costs;

    (vi) Projects needed mainly for fire protection.