No. 37196 (Amendment): Rule R313-24. Uranium Mills and Source Material Mill Tailings Disposal Facility Requirements  

  • (Amendment)

    DAR File No.: 37196
    Filed: 01/11/2013 10:06:23 AM

    RULE ANALYSIS

    Purpose of the rule or reason for the change:

    Changes are required to conform with S.B. 21, 2012 General Session (Chapter 360, Laws of Utah 2012).

    Summary of the rule or change:

    S.B. 21 (2012) gave authority to the Director of the Division of Radiation Control to make many regulatory decisions that had previously been made either by the Radiation Control Board or by the Executive Secretary of the Radiation Control Board. This rule change implements these statutory changes by replacing occurrences of both "executive secretary" and "board" with "director."

    State statutory or constitutional authorization for this rule:

    Anticipated cost or savings to:

    the state budget:

    There are no anticipated costs or savings to the state budget as this amendment only changes who has authority to make regulatory decisions.

    local governments:

    There are no anticipated costs or savings as this amendment only changes who has authority to make regulatory decisions.

    small businesses:

    There are no anticipated costs or savings as this amendment only changes who has authority to make regulatory decisions.

    persons other than small businesses, businesses, or local governmental entities:

    There are no anticipated costs or savings as this amendment only changes who has authority to make regulatory decisions.

    Compliance costs for affected persons:

    There are no compliance costs for affected persons as this amendment only changes who has authority to make regulatory decisions.

    Comments by the department head on the fiscal impact the rule may have on businesses:

    There is no anticipated fiscal impact on businesses as this amendment only changes who has authority to make regulatory decisions.

    Amanda Smith, Executive Director

    The full text of this rule may be inspected, during regular business hours, at the Division of Administrative Rules, or at:

    Environmental Quality
    Radiation ControlRoom Third Floor
    195 N 1950 W
    SALT LAKE CITY, UT 84116-3085

    Direct questions regarding this rule to:

    Interested persons may present their views on this rule by submitting written comments to the address above no later than 5:00 p.m. on:

    03/04/2013

    This rule may become effective on:

    03/19/2013

    Authorized by:

    Rusty Lundberg, Director

    RULE TEXT

    R313. Environmental Quality, Radiation Control.

    R313-24. Uranium Mills and Source Material Mill Tailings Disposal Facility Requirements.

    R313-24-1. Purpose and Authority.

    (1) The purpose of this rule is to prescribe requirements for possession and use of source material in milling operations such as conventional milling, in-situ leaching, or heap-leaching. The rule includes requirements for the possession of byproduct material, as defined in Section R313-12-3 (see "byproduct material" definition (b)), from source material milling operations, as well as, possession and maintenance of a facility in standby mode. In addition, requirements are prescribed for the receipt of byproduct material from other persons for possession and disposal. The rule also prescribes requirements for receipt of byproduct material from other persons for possession and disposal incidental to the byproduct material generated by the licensee's source material milling operations.

    (2) The rules set forth herein are adopted pursuant to the provisions of Subsections 19-3-104(4) and 19-3-104(8).

    (3) The requirements of Rule R313-24 are in addition to, and not substitution for, the other applicable requirements of Title R313. In particular, the provisions of Rules R313-12, R313-15, R313-18, R313-19, R313-21, R313-22, and R313-70 apply to applicants and licensees subject to Rule R313-24.

     

    R313-24-2. Scope.

    (1) The requirements in Rule R313-24 apply to source material milling operations, byproduct material, and byproduct material disposal facilities.

     

    R313-24-3. Environmental Analysis.

    (1) Each new license application, renewal, or major amendment shall contain an environmental report describing the proposed action, a statement of its purposes, and the environment affected. The environmental report shall present a discussion of the following:

    (a) An assessment of the radiological and nonradiological impacts to the public health from the activities to be conducted pursuant to the license or amendment;

    (b) An assessment of any impact on waterways and groundwater resulting from the activities conducted pursuant to the license or amendment;

    (c) Consideration of alternatives, including alternative sites and engineering methods, to the activities to be conducted pursuant to the license or amendment; and

    (d) Consideration of the long-term impacts including decommissioning, decontamination, and reclamation impacts, associated with activities to be conducted pursuant to the license or amendment.

    (2) Commencement of construction prior to issuance of the license or amendment shall be grounds for denial of the license or amendment.

    (3) The [Executive Secretary]Director shall provide a written analysis of the environmental report which shall be available for public notice and comment pursuant to R313-17-2.

     

    R313-24-4. Clarifications or Exceptions.

    For the purposes of Rule R313-24, 10 CFR 40.2a through 40.4; 40.12; 40.20(a); 40.21; 40.26(a) through (c); 40.31(h); 40.41(c); the introduction to 40.42(k) and 40.42(k)(3)(i); 40.61(a) and (b); 40.65; and Appendix A to Part 40(2002) are incorporated by reference with the following clarifications or exceptions:

    (1) The exclusion and substitution of the following:

    (a) Exclude 10 CFR 40.26(c)(1) and replace with "(1) The provisions of Sections R313-12-51, R313-12-52, R313-12-53, R313-19-34, R313-19-50, R313-19-61, R313-24-1, Rules R313-14, R313-15, R313-18, and R313-24 (incorporating 10 CFR 40.2a, 40.3, 40.4, and 40.26 by reference)";

    (b) In Appendix A to 10 CFR 40, exclude Criterion 5B(1) through 5H, Criterion 7A, Criterion 13, and replace the excluded Criterion with "Utah Administrative Code, R317-6, Ground Water Quality Protection"; and

    (c) In Appendix A to 10 CFR 40, exclude Criterion 11A through 11F and Criterion 12;

    (2) The substitution of the following:

    (a) "10 CFR 40" for reference to "this part" as found throughout the incorporated text;

    (b) "[Executive Secretary]Director" for reference to "Commission" in the first and fourth references contained in 10 CFR 40.2a, in 10 CFR 40.3, 40.20(a), 40.26, 40.41(c), 40.61, and 40.65;

    (c) "Rules R313-19, R313-21, or R313-22" for "Section 62 of the Act" as found in 10 CFR 40.12(a);

    (d) "Rules R313-21 or R313-22" for reference to "the regulations in this part" in 10 CFR 40.41(c);

    (e) "Section R313-19-100" for reference to "part 71 of this chapter" as found in 10 CFR 40.41(c);

    (f) In 10 CFR 40.42(k)(3)(i), "R313-15-401 through R313-15-406" for reference to "10 CFR part 20, subpart E";

    (g) "source material milling" for reference to "uranium milling, in production of uranium hexafluoride, or in a uranium enrichment facility" as found in 10 CFR 40.65(a);

    (h) "[Executive Secretary]Director" for reference to "appropriate NRC Regional Office shown in Appendix D to 10 CFR part 20 of this chapter, with copies to the Director, Office of Nuclear Material Safety and Safeguards, U.S. Nuclear Regulatory Commission, Washington, DC 20555," as stated in 10 CFR 65(a)(1);

    (i) "require the licensee to" for reference to "require to" in 10 CFR 40.65(a)(1); and

    (j) In Appendix A to 10 CFR part 40, the following substitutions:

    (i) "R313-12-3" for reference to "Sec. 20.1003 of this chapter" as found in the first paragraph of the introduction to Appendix A;

    (ii) "Utah Administrative Code, Rule R317-6, Ground Water Quality Protection" for ground water standards in "Environmental Protection Agency in 40 CFR part 192, subparts D and E" as found in the Introduction, paragraph 4; or "Environmental Protection Agency in 40 CFR part 192, subparts D and E (48 FR 45926; October 7, 1983)" as found in Criterion 5;

    (iii) "[Board]Director as defined in Subsection 19-5-102(6)" for reference to "Commission" in the definition of "compliance period," in paragraph five of the introduction and in Criterion 5A(3);

    (iv) "[Executive Secretary]Director" for reference to "Commission" in the definition of "closure plan", in paragraph five of the introduction, and in Criterions 6(2), 6(4), 6(6), 6A(2), 6A(3), 9, and 10 of Appendix A;

    (v) "license issued by the [Executive Secretary]Director" for reference to "Commission license" in the definition of "licensed site," in the introduction to Appendix A;

    (vi) "[Executive Secretary]Director" for reference to "NRC" in Criterion 4D;

    (vii) "representatives of the [Executive Secretary]Director" for reference to "NRC staff" in Criterion 6(6);

    (viii) "[Executive Secretary]Director-approved" for reference to "Commission-approved" in Criterion 6A(1) and Criterion 9;

    (ix) "[Executive Secretary]Director" for reference to "appropriate NRC regional office as indicated in Criterion 8A" as found, Criterion 8, paragraph 2 or for reference to "appropriate NRC regional office as indicated in Appendix D to 10 CFR part 20 of this chapter, or the Director, Office of Nuclear Material Safety and Safeguards, U.S. Nuclear Regulatory Commission, Washington, DC 20555," as stated in Criterion 8A; and

    (x) "[Executive Secretary]Director" for reference to "the Commission or the State regulatory agency" in Criterion 9, paragraph 2.

     

    KEY: environmental analysis, uranium mills, tailings, monitoring

    Date of Enactment or Last Substantive Amendment: [October 7, 2002]2013

    Notice of Continuation: May 24, 2012

    Authorizing, and Implemented or Interpreted Law: 19-3-104; 19-3-108

     


Document Information

Effective Date:
3/19/2013
Publication Date:
02/01/2013
Filed Date:
01/11/2013
Agencies:
Environmental Quality,Radiation Control
Rulemaking Authority:

Section 19-3-104

Section 19-3-108

Authorized By:
Rusty Lundberg, Director
DAR File No.:
37196
Related Chapter/Rule NO.: (1)