Utah Administrative Code (Current through November 1, 2019) |
R930. Transportation, Preconstruction |
R930-8. Utility Relocations Required by Highway Projects |
R930-8-10. Issuance of Administrative Order; Enforcement
-
(1) In the event that a Utility fails to timely coordinate and cooperate with the Department at any point in the utility relocation process, the Department may issue an administrative order pursuant to Utah Code Section 72-6-116(2)(b) to the Utility to accommodate the highway project. The administrative order shall be issued by the Department's Statewide Railroad and Utilities Director and will include a reasonable timeframe for Utility Company actions to be complete the relocation of the utility facilities, including any design.
(2) If the Utility fails to comply with the Department's administrative order, and the failure to comply is not caused by a third party who the Utility has no control over, the Department may issue an administrative order to remedy non-compliance. The Department may order any or all the following remedies:
(a) The Department may recover from the Utility increased costs caused by the Utility's unreasonable or unjustified delays. Such actual and indirect costs may include, but are not limited to, increased costs on the current highway project or related projects, added expenses from loss of a construction season, and loss of project funding.
(b) The Department may deny further permits for utility installation under R930-7 until the Utility's non-compliance is resolved.
(c) The Department may perform design work and construction work on behalf of the Utility for those utility facilities located within the highway right-of-way, except for fiber for telecommunications, electricity, and natural gas. The Department will only perform such work if the work can be performed without violating any state or federal statute, regulation, or safety requirement. The Utility shall reimburse the Department for the costs the Department incurs to relocate the Utility's facilities, in amounts allowed by Utah Code Section 72-6-116(3).
(3) In addition, the Department may pursue additional remedies or claims against a Utility in a district court in Utah.
(4) The Department shall not limit or waive any of its remedies or claims allowed in this rule or law.
(5) The Department may require a Utility to comply with a practicable shortened process or expedited schedule when an emergency exists that could affect public safety or the structural or functional integrity of the highway.