R920-50-8. Documents Required for Ropeways
-
(1) A Utah Passenger Ropeway Safety Committee Lift Data Form must be submitted along with other requested supporting documents. This form must be submitted prior to the performance of the Acceptance Test.
(2) A copy of the acceptance test procedure proposed and submitted by the designer or manufacturer must be provided to the Committee for review at least fourteen (14) days before acceptance testing begins. The qualified engineer determines the acceptance test requirements.
(3) The owner or area operator shall notify the Committee in writing before the acceptance test that the continuous operation requirements of ANSI B77.1 section X.1.1.11 or ANSI B77.2 section 2.1.1.11 have been completed.
(4) A final acceptance test report must be submitted to the Committee prior to opening the lift to the public. The qualified engineer shall approve any changes to the acceptance test procedure.
(5) "As-built" drawings for each passenger ropeway shall be submitted no later than 60 days after the project is completed and the Acceptance Test is finished. Any variation from the design drawings shall be noted in the as-built drawings and approved by the Qualified Design Engineer.
(6) The area operator shall send a "letter of intent" to the Committee at least 45 days prior to beginning the construction of a new lift. The letter of intent must include the name of the qualified engineer, the design standard, the anticipated dates to begin and complete construction, and the available lift manufacturing data.