R918-5-2. Purpose and Background  


Latest version.
  •   Section 72-6-107 requires that any construction or improvement project whose estimated cost for labor and materials exceeds the Bid Limit defined in Section 72-6-109 shall be performed under contract awarded to the lowest responsible bidder. Construction or improvement projects with estimated costs for labor and materials lower than that Bid Limit may be performed by force account. That same section also directs the Department to establish a procedure whereby evidence that a region violated that law may be heard, and also directs the Department to establish sanctions for a region found to be in violation. This rule establishes those procedures and sanctions.