R746-430-2. Approval of a Significant Energy Resource  


Latest version.
  • (1) Filing Requirements- When an Affected Utility files a request to approve a Significant Energy Resource pursuant to Section 54-17-302, the utility shall include with its request the following:

    (a) Information to demonstrate the utility has complied with the requirements of the Energy Resource Procurement Act and Commission rules;

    (b) Information to demonstrate whether approval of the selected Significant Energy Resource is in the public interest;

    (c) Information regarding the solicitation process, if the Significant Energy Resource was solicited through a solicitation process, including, but not limited to:

    (i) Summaries of all bids received;

    (ii) Summaries of the Affected Utility's rankings and evaluations of bids;

    (iii) Copies of all reports relating to the solicitation process made by an independent evaluator who may have been involved with the solicitation process;

    (iv) A copy of the complete Commission approved Solicitation with appendices, attachments and drafts, if applicable; and

    (v) A signed acknowledgment from a utility officer involved in the solicitation that to the best of his or her knowledge, the utility fully observed and complied with the requirements of the Commission's rules or statutes applicable to the solicitation process;

    (d) Identification of all information, data, models and analyses used by the Affected Utility to evaluate the acquisition of the Significant Energy Resource if the acquisition is pursuant to Section 54-17-201(3), or to evaluate and rank bids and the selected resource, if the acquisition is by a solicitation process pursuant to Section 54-17-201(2);

    (e) Contracts proposed for execution or use in connection with the acquisition of the Significant Energy Resource and identification of matters for which contracts are being negotiated or remain to be negotiated;

    (f) Information on the estimated costs for the Significant Energy Resource, including but not limited to engineering studies, data, and models used in the analysis, and any other costs which the utility considers recoverable pursuant to Section 54-17-303;

    (g) An analysis of the estimated effects the Significant Energy Resource will have on the Affected Utility's revenue requirement;

    (h) Financial information demonstrating adequate financial capability to obtain the Significant Energy Resource pursuant to the proposed acquisition;

    (i) Identification of all other relevant information in support of the requested approval; and

    (j) If the Commission has not previously issued a Protective Order in the approval request proceeding, a Proposed Protective Order, using the Commission's standard Protective Order, which may be used to facilitate access to information which may be claimed as confidential or protected.

    (2) Procedure to Approve a Significant Energy Resource and Its Acquisition.

    (a) If the Affected Utility is contemplating acquiring a Significant Energy Resource through a solicitation process, after it has completed its evaluation of bids but prior to filing a request to approve a Significant Energy Resource, the utility shall provide a written notification to the Commission of the Significant Energy Resources it has selected from the bids and the reasoning for the utility's selection of those resources.

    (b) The Affected Utility may negotiate a proposed final agreement for the acquisition of the proposed Significant Energy Resource at any time, however, any such agreement shall be expressly conditional on the final decision of the Commission in the approval proceeding.

    (c) The Affected Utility shall file a request for approval of a Significant Energy Resource as soon as practicable after completion of the utility's decision to select the resource.

    (i) Prior to filing the request for approval of a Significant Energy Resource, the Affected Utility shall provide public notice of its intent to file the request and seek approval of the Significant Energy Resource from the Commission.

    (ii) After the filing of the request, the Commission will schedule and provide notice of a Scheduling Conference to set a schedule for the proceedings, including a public hearing, through which it will consider the requested approval of the Significant Energy Resource.

    (d) Any agreement for the acquisition of a Significant Energy Resource shall be submitted to the Commission for approval. The Commission will set a schedule to accept comments and reply comments from interested persons and the Affected Utility concerning whether the agreement complies with any Commission orders or Commission conditions relating to the Significant Energy Resource which will be acquired through the agreement.

    (e) The Affected Utility shall maintain a complete record of analyses and evaluations, including spreadsheets and models materially relied upon by the utility, all materials submitted to the Commission and the Independent Evaluator and all materials submitted in response to discovery requests during any proceedings to approve a Significant Energy Resource and its acquisition for at least ten years after the date of a Commission order approving an agreement to acquire the Significant Energy Resource. A party to a proceeding may petition the Commission to require specified additional material to be maintained for a specified time.