R746-409-4. Reporting and Notification Requirements  


Latest version.
  •   A. An operator must comply with the notification and reporting requirements contained in Part 191 and Section R746-409-4.

      B. Telephonic notification to the Division.

      1. For incidents requiring immediate notice under Part 191.5, an operator must also provide contemporaneous telephonic notification of the same information required under Part 191.5 to the Division at (844)-GAS-2525 or (844)-427-2525.

      2. State Reportable Incidents. An operator must provide telephonic notice to the Division at (844)-GAS-2525 or (844)-427-2525 of all state reportable incidents, including the location and known details at the time of reporting, at the earliest practicable moment when safely possible following discovery.

      C. Written Reports required by Part 191. For all reports required under Part 191, including updates and supplemental reports, an operator shall contemporaneously furnish these reports to the Commission and the Division in accordance with Section R746-409-4.F.

      D. Excavation Damage Quarterly Report. Each operator with more than 10,000 customers shall file a quarterly excavation damage report within 60 days after the end of the each quarter with the Commission and the Division in accordance with Section R746-409-4.F on a form approved by the Division.

      E. Reports Relating to Safety Issues. An operator shall prepare and file reports relating to safety issues as requested and described by the Commission or the Division in accordance with Section R746-409-4-F.

      F. Filing of Written Reports:

      1. All required written reports shall be filed with the Commission in accordance with Commission's filing requirements posted on the Commission's website at http://www.psc.utah.gov at the "Filing Req" tab under the Document column labeled "Pipeline Safety."

      2. All required written reports shall be filed electronically with the Division at the following e-mail address: pipelinesafety@utah.gov.