R455-11-6. Execution of Project  


Latest version.
  • (1) During the course of the project, the Office shall be available for continuing consultation subject to budgetary and management constraints. If the applicant desires to modify the approved work plan, the applicant shall make such request for a change on a form approved by the Office and shall be governed by the provisions of R455-11-5.

    (2) The applicant shall allow access and observation of the project building at any reasonable time upon request of the Office.