R357-24-110. Funding Distribution  


Latest version.
  •   (1) TRU shall reimburse the awardee for no more than the total amount specified in the contract.

      (2) Payment will only be made for those costs authorized and approved by TRU after providing sufficient documentation in accordance with the terms and conditions provided in the contract.

      (3) After execution of the contract between GOED and awardee:

      (a) awardee may receive up to fifty percent of the total grant amount, subject to TRU approval;

      (b) remaining funds to be disbursed on a reimbursement basis, as outlined in scope of work and after company provides sufficient evidence of initial expenditures.

      (4) Failure to successfully complete the scope of work requirements may result in a recapture of all or part of the grant funding and will be grounds to terminate the contract and any future funding.