R317-801-2. General Permit Requirements  


Latest version.
  • 2.1 General Permit for sewer collection system. All permittees are required to operate under the General Permit for sewer collection systems as required by this rule, R317-801.

    2.2 Notice of Intent Requirements.

    (1) A permittee shall submit a Notice of Intent to be covered by the General Permit for sewer collection systems between October 1, 2012 and November 30, 2012. A new permittee for a sewer collection system shall submit a Notice of Intent to be covered by the General Permit for sewer collection systems at least three (3) months prior to operation of the system.

    (2) Forms and instructions for submitting a Notice of Intent can be obtained online on the DWQ's website.

    2.3 Effective Date of General Permit.

    General permit coverage will be in effect when the Notice of Intent has been submitted, approved and declared complete by the Executive Secretary.