R317-8-6. Review Procedures  


Latest version.
  • 6.1 REVIEW OF THE APPLICATION

    (1) Any person who requires a permit under the UPDES program shall complete, sign and submit to the Director an application for the permit as required under R317-8-3.1. Applications are not required for UPDES general permits. (However, operators who elect to be covered by a general permit shall submit written notification to the Director at such time as the Director indicates in R317-8-6.3)

    (2) The Director will not begin the processing of a permit until the applicant has fully complied with the application requirements for the permit, as required by R317-8-3.1; or for concentrated animal feeding operations, as required by R317-8-10.

    (3) Permit applications must comply with the signature and certification requirements of R317-8-3.1.

    (4) Each application submitted by a UPDES new source or UPDES new discharger should be reviewed for completeness by the Director within thirty (30) days of its receipt. Each application for a UPDES permit submitted by an existing source or sludge-only facility will be reviewed for completeness within sixty (60) days of receipt. Upon completing the review, the Director shall notify the applicant in writing whether the application is complete. If the application is incomplete, the Director shall list the information necessary to make the application complete. When the application is for an existing source or sludge-only facility, the Director shall specify in the notice of deficiency a date for submitting the necessary information. The Director shall notify the applicant that the application is complete upon receiving this information. After the application is completed, the Director may request additional information from an applicant when necessary to clarify, modify, or supplement previously submitted material. Requests for such additional information will not render an application incomplete.

    (5) If an applicant fails or refuses to correct deficiencies in the application, the permit may be denied and appropriate enforcement actions may be taken under the Utah Water Quality Act, as amended and rules promulgated pursuant thereto.

    (6) If the Director decides that a site visit is necessary for any reason in conjunction with the processing of an application, the applicant will be notified and a date scheduled.

    (7) The effective date of an application is the date on which the Director notified the applicant that the application is complete as provided in subsection (4) of this section.

    (8) For each application from a major facility new source, or major facility new discharger, the Director shall no later than the effective date of the application, prepare and mail to the applicant a project decision schedule. The schedule will specify target dates by which the Director intends to:

    (a) Prepare a draft permit;

    (b) Give public notice;

    (c) Complete the public comment period, including any public hearing;

    (d) Issue a final permit; and

    6.2 REVIEW PROCEDURES FOR PERMIT MODIFICATION, REVOCATION AND REISSUANCE, OR TERMINATION OF PERMITS

    (1) Permits may only be modified, revoked and reissued, or terminated for the reasons specified in R317-8-5.6. Permits may be modified, revoked and reissued, or terminated either at the request of any interested person (including the permittee) or upon the Director's initiative. All requests shall be in writing and shall contain facts or reasons supporting the request.

    (2) If the Director decides the request is not justified, he or she shall send the requester a brief written response giving a reason for the decision. Denials of requests for modification, revocation and reissuance, or termination are not subject to public notice, comment, or adjudicatory proceeding.

    (3) If the Director tentatively decides to modify or revoke and reissue a permit under R317-8-5.6, he or she shall prepare a draft permit under R317-8-6.3 incorporating the proposed changes. The Director may request additional information and, in the case of a modified permit, may require the submission of an updated application. In the case of revoked and reissued permits, the Director shall require the submission of a new application.

    (a) In a permit modification under .2, only those conditions to be modified will be reopened when a new draft permit is prepared. All other aspects of the existing permit shall remain in effect for the duration of the unmodified permit. When a permit is revoked and reissued under .2, the entire permit is reopened just as if the permit had expired and was being reissued. During any revocation and reissuance proceeding, the permittee shall comply with all conditions of the existing permit until a new final permit is reissued.

    (b) "Minor modifications" as defined in R317-8-5.6(3) are not subject to the requirements of .2.

    (4) If the Director tentatively decides to terminate a permit under R317-8-5.7, he or she shall issue a notice of intent to terminate. A notice of intent to terminate is a type of draft permit which follows the same procedures as any draft permit prepared under R317-8-6.3.

    6.3 DRAFT PERMITS

    (1) Once an application is complete, the Director shall tentatively decide whether to prepare a draft permit or to deny the application.

    (2) If the Director tentatively decides to deny the permit application, then he or she shall issue a notice of intent to deny. A notice of intent to deny the permit application is a type of draft permit which follows the same procedure as any draft permit prepared under this section. If the Director's final decision (under R317-8-6.11) is that the tentative decision to deny the permit application was incorrect, he or she shall withdraw the notice of intent to deny and proceed to prepare a draft permit under R317-8-6.3(4).

    (3) If the Director tentatively decides to issue a UPDES general permit, he or she shall prepare a draft general permit in accordance with R317-8-6.3(4).

    (4) If the Director decides to prepare a draft permit he or she shall prepare a draft permit that contains the following information:

    (a) All conditions under R317-8-4.1;

    (b) All compliance schedules under R317-8-5.2;

    (c) All monitoring requirements under R317-8-5.3;

    (d) Effluent limitations, standards, prohibitions, standards for sewage sludge use or disposal, and conditions under R317-8-3, 8-4, 8-5, 8-6, and 8-7 and all variances that are to be included.

    (5) All draft permits prepared under this section shall be accompanied by a statement of basis or fact sheet and shall be based on the administrative record, publicly noticed, and made available for public comment. The Director will give notice of opportunity for a public hearing, issue a final decision and respond to comments.

    (6) Statement of Basis. A statement of basis shall be prepared for every draft permit for which a fact sheet is not prepared. The statement of basis shall briefly describe the derivation of the conditions of the draft permit and the reasons for them or, in the case of notices of intent to deny or terminate, reasons supporting the tentative decision. The statement of basis shall be sent to the applicant and, on request, to any other person.

    6.4 FACT SHEETS

    (1) A fact sheet shall be prepared for every draft permit for a major UPDES facility or activity, for every UPDES general permit, for every UPDES draft permit that incorporates a variance or requires an explanation under R317-8-6.4(4), for every Class I Sludge Management Facility, for every draft permit that includes a sewage sludge land application plan and for every draft permit which the Director finds is the subject of widespread public interest or raises major issues. The fact sheet shall briefly set forth the principal facts and the significant factual, legal, methodological and policy questions considered in preparing the draft permit. The Director shall send this fact sheet to the applicant and, on request, to any other persons.

    (2) The fact sheet shall include, when applicable:

    (a) A brief description of the type of facility or activity which is the subject of the draft permit;

    (b) The type and quantity of wastes, fluids or pollutants which are proposed to be or are being treated, stored, disposed of, injected, emitted, or discharged;

    (c) A brief summary of the basis for the draft permit conditions including references to applicable statutory or regulatory provisions;

    (d) Reasons why any requested variances or alternatives to required standards do or do not appear justified;

    (e) A description of the procedures for reaching a final decision on the draft permit including:

    1. The beginning and ending dates of the comment period and the address where comments will be received;

    2. Procedures for requesting a public hearing and the nature of that hearing; and

    3. Any other procedures by which the public may participate in the final decision.

    (f) Name and telephone number of a person to contact for additional information.

    (3) Any calculations or other necessary explanation of the derivation of specific effluent limitations and conditions, or standards for sewage sludge use and disposal, including a citation to the applicable effluent limitation guideline or performance standard provisions, and reasons why they are applicable or an explanation of how the alternate effluent limitations were developed;

    (4)(a) When the draft permit contains any of the following conditions, an explanation of the reasons why such conditions are applicable:

    1. Limitations to control toxic pollutants under R317-8-4.2(5);

    2. Limitations on internal waste streams under R317-8-4.3(8);

    3. Limitations on indicator pollutant;

    4. Limitations set on a case-by-case basis under R317-8-7.1(3)(b) or (c).

    (b) For every permit to be issued to a treatment works owned by a person other than the State or a municipality, an explanation of the Director's decision on regulation of users under R317-8-4.2(12).

    (5) When appropriate, a sketch or detailed description of the location of the discharge or regulated activity described in the application.

    (6) For permits that include a sewage sludge land application plan, a brief description of how each of the required elements of the land application plan are addressed in the permit.

    (7) Any calculations or other necessary explanation of the derivation of specific effluent limitations and conditions or standards for sewage sludge use or disposal, including a citation to the applicable effluent limitation guideline, performance standard, or standard for sewage sludge use or disposal and reasons why they are applicable or an explanation of how the alternate effluent limitations were developed.

    6.5 PUBLIC NOTICE OF PERMIT ACTIONS AND PUBLIC COMMENT PERIOD

    (1) Scope.

    (a) The Director will give public notice that the following actions have occurred:

    1. A permit application has been tentatively denied under R317-8-6.3(2); or

    2. A draft permit has been prepared under R317-8-6.3(4);

    3. A public hearing has been scheduled under R317-8-6.7; and

    4. A UPDES new source determination has been made in accordance with the definition in R317-8-1.

    (b) No public notice is required when a request for permit modification, revocation and reissuance, or termination is denied under .2. Written notice of the denial will be given to the requester and to the permittee.

    (c) Public notices may describe more than one permit or permit action.

    (2) Timing.

    (a) Public notice of the preparation of a draft permit, including a notice of intent to deny a permit application, required under R317-8-6.5(1) will allow at least thirty (30) days for public comment.

    (b) Public notice of a public hearing shall be given at least thirty (30) days before the hearing. (Public notice of the hearing may be given at the same time as public notice of the draft permit and the two notices may be combined.)

    (3) Methods. Public notice of activities described in R317-8-6.5(1)(a) will be given by the following methods:

    (a) By mailing a copy of a notice to the following persons (Any person otherwise entitled to receive notice under this paragraph may waive their rights to receive notice for any classes and categories of permits.):

    1. The applicant, except for UPDES general permittees, and Region VIII, EPA.

    2. Federal and state agencies with jurisdiction over fish, shellfish, and wildlife resources, the Advisory Council on Historic Preservation, Utah Historic Society and other appropriate government authorities, including any affected states;

    3. The U.S. Army Corps of Engineers and the U.S. Fish and Wildlife Service.

    4. Any user identified in the permit application of a privately owned treatment works; and

    5. Persons on a mailing list developed by:

    a. Including those who request in writing to be on the list;

    b. Soliciting persons for area lists from participants in past permit proceedings in that area; and

    c. Notifying the public of the opportunity to be put on the mailing list through periodic publication in the public press and in such publications as newsletters, environmental bulletins, or state law journals. The Director may update the mailing list from time to time by requesting written indication of continued interest from those listed. The name of any person who fails to respond to such a request may be deleted from the list.

    6. Any unit of local government having jurisdiction over the area where the facility is proposed to be located and each State agency having any authority under State law with respect to construction or operation of such facility.

    7. Any other agency which the Director knows has issued or is required to issue a RCRA, UIC, PSD (or other permit under the Federal Clean Air Act, NPDES, 404, or sludge management permit).

    (b) For major permits, UPDES general permits, and permits that include sewage sludge and application plans, the Director will publish a notice in a daily or weekly newspaper within the area affected by the facility or activity;

    (c) In a manner constituting legal notice to the public under Utah law; and

    (d) Any other method reasonably determined to give actual notice of the action in question to the persons potentially affected by it, including press releases or any other forum or medium to elicit public participation.

    (4) Contents.

    (a) All public notices issued under this part shall contain the following minimum information:

    1. Name and address of the office processing the permit action for which notice is being given;

    2. Name and address of the permittee or permit applicant and, if different, of the facility or activity regulated by the permit, except in the case of UPDES draft general permits under R317-8-2.5;

    3. A brief description of the business conducted at the facility or activity described in the permit application or the draft permit, for UPDES general permits when there is no application;

    4. Name, address and telephone number of a person from whom interested persons may obtain further information, including copies of the draft permit or draft general permit as the case may be, statement of basis or fact sheet, and the application; and

    5. A brief description of the comment procedures and the time and place of any public hearing that will be held, including a statement of procedures to request a public hearing, unless a hearing has already been scheduled, and other procedures by which the public may participate in the final permit decision;

    6. For UPDES permits only (including those for sludge-only facilities), a general description of the location of each existing or proposed discharge point and the name of the receiving water and the sludge use and disposal practice(s) and the location of each sludge treatment works treating domestic sewage and use or disposal sites known at the time of permit application. For draft general permits, this requirement will be satisfied by a map or description of the permit area;

    7. Any additional information considered necessary or appropriate.

    (b) Public notices for public hearings. In addition to the general public notice described in .5(4) the public notice for a permit hearing under R317-8-6.7 will contain the following information:

    1. Reference to the date of previous public notices relating to the permit;

    2. Date, time, and place of the hearing;

    3. A brief description of the nature and purpose of the hearing, including the applicable rules and procedures.

    (c) Requests under R317-8-2.3(4). In addition to the information required under R317-8-6.5(4)(a) public notice of a UPDES draft permit for a discharge when a R317-8-2.3(4) request has been filed will include:

    1. A statement that the thermal component of the discharge is subject to effluent limitations under R317-8-4.2(1) and a brief description, including a quantitative statement of the thermal effluent limitations; and

    2. A statement that a R317-8-2.3(4) request has been filed and that alternative less stringent effluent limitations may be imposed on the thermal component of the discharge and a brief description, including a quantitative statement, of the alternative effluent limitations, if any, included in the request.

    3. If the applicant has filed an early screening request under R317-8-7.4(4) for a variance, a statement that the applicant has submitted such a plan.

    (5) In addition to the general public notice described in .5(4) all persons identified in .5(3)(a)1-4 will be mailed a copy of the fact sheet, the permit application and the draft permit.

    6.6 PUBLIC COMMENTS AND REQUESTS FOR PUBLIC HEARINGS

    During the public comment period provided under R317-8-6.5, any interested person may submit written comments on the draft permit and may request a public hearing, if no hearing has already been scheduled. A request for a public hearing shall be in writing and shall state the nature of the issues proposed to be raised in the hearing. All comments will be considered in making the final decision and shall be answered as provided in R317-8-6.12.

    6.7 PUBLIC HEARINGS

    (1) The Director shall hold a public hearing when he or she finds on the basis of request(s), a significant degree of public interest in draft permits. The Director also may hold a public hearing at his or her discretion whenever a hearing might clarify one or more issues involved in the permit decision.

    (2) Public notice of the hearing will be given as specified in R317-8-6.5.

    (3) Any person may submit oral or written statements and data concerning the draft permit. Reasonable limits may be set upon the time allowed for oral statements, and the submission of statements in writing may be required. The public comment period under R317-8-6.5 will automatically be extended to the close of any public hearing under this section. The hearing officer may also extend the comment period by so stating at the hearing.

    (4) A tape recording or written transcript of the hearing shall be made available to the public.

    6.8 OBLIGATION TO RAISE ISSUES AND PROVIDE INFORMATION DURING THE PUBLIC COMMENT PERIOD

    All persons, including applicants, who believe any condition of a draft permit is inappropriate or that the Director's tentative decision to deny an application, terminate a permit, or prepare a draft permit is inappropriate, must raise all reasonably ascertainable issues and submit all reasonably available arguments and factual grounds supporting their position, including all supporting material, by the close of the public comment period including any public hearing under R317-8-6.5. All supporting materials shall be included in full and may not be incorporated by reference, unless they are already part of the administrative records in the same proceeding or consist of state or federal statutes and regulations, EPA or the Director's documents of general applicability, or other generally available reference materials. Persons making comment shall make supporting material not already included in the administrative record available to the Director. Additional time shall be granted under R317-8-6.5 to the extent that a person desiring to comment who requests additional time demonstrates need for such time.

    6.9 CONDITIONS REQUESTED BY THE CORPS OF ENGINEERS AND OTHER GOVERNMENT AGENCIES

    (1) If, during the comment period for a UPDES draft permit, the District Engineer of the Corps of Engineers advises the Director in writing that anchorage and navigation of the waters of the State would be substantially impaired by the granting of a permit, the permit shall be denied and the applicant so notified. If the District Engineer advises the Director that imposing specified conditions upon the permit is necessary to avoid any substantial impairment of anchorage or navigation, then the Director shall include the specified conditions in the permit. Review or appeal of denial of a permit or of conditions specified by the District Engineer shall be made through the applicable procedures of the Corps of Engineers and may not be made through the procedures provided in this rule. If the conditions are stayed by a court of competent jurisdiction or by applicable procedures or the Corps of Engineers, those conditions shall be considered stayed in the UPDES permit for the duration of that stay.

    (2) If, during the comment period, the U.S. Fish and Wildlife Service or any other state or federal agency with jurisdiction over fish, wildlife, or public health advises the Director in writing that the imposition of specified conditions upon the permit is necessary to avoid substantial impairment of fish, shellfish, or wildlife resources, the Director may include the specified conditions in the permit to the extent they are determined necessary to carry out the provisions of the Utah Water Quality Act, as amended, and of CWA.

    (3) In appropriate cases the Director may consult with one or more of the agencies referred to in this section before issuing a draft permit and may reflect their views in the statement of basis or fact sheet, or the draft permit.

    6.10 REOPENING OF THE PUBLIC COMMENT PERIOD

    (1) The Director may order the public comment period reopened if the procedures of this section could expedite the decision making process. When the public comment period is reopened under this paragraph, all persons, including applicants, who believe any condition of a draft permit is inappropriate or that the Director's tentative decision to deny an application, terminate a permit, or prepare a draft permit is inappropriate, must submit all reasonably available factual grounds supporting their position, including all supporting material, by a date not less than sixty days after public notice under paragraph (2) of this section, set by the Director. Thereafter, any person may file a written response to the material filed by any other person, by a date not less than twenty days after the date set for filing of the material, set by the Director.

    (2) Public notice of any comment period under this paragraph shall identify the issues to which the requirements of this section shall apply.

    (3) On his own motion or on the request of any person, the Director may direct that the requirements of paragraph (1) of this section shall apply during the initial comment period where it reasonably appears that issuance of the permit will be contested and that applying the requirements of paragraph (1) of this section will substantially expedite the decision making process. The notice of the draft permit shall state whenever this has been done.

    (4) A comment period of longer than 60 days will often be necessary in complicated proceedings to give persons desiring to comment a reasonable opportunity to comply with the requirements of this section. Persons desiring to comment may request longer comment periods and they shall be granted under R317-8-6.5 to the extent they appear necessary.

    (5) If any data information or arguments submitted during the public comment period, including information or arguments required under R317-8-6.8, appear to raise substantial new questions concerning a permit, the Director may take one or more of the following actions:

    (a) Prepare a new draft permit, appropriately modified, under R317-8-6.3;

    (b) Prepare a revised statement of basis under R317-8-6.3(6) a fact sheet or revised fact sheet under R317-8-6.4 and reopen the comment period under R317-8-6.10; or

    (c) Reopen or extend the comment period under R317-8-6.5 to give interested persons an opportunity to comment on the information or arguments submitted.

    (6) Comments filed during the reopened comment period shall be limited to the substantial new questions that caused its reopening. The public notice under R317-8-6.5 shall define the scope of the reopening.

    (7) For UPDES permits, the Director may also, in the circumstances described above, elect to hold further proceedings. This decision may be combined with any of the actions enumerated in paragraph (5) of this section.

    (8) Public notice of any of the above actions shall be issued under R317-8-6.5.

    6.11 ISSUANCE AND EFFECTIVE DATE OF PERMIT

    After the close of the public comment period under R317-8-6.5, the Director will issue a final permit decision. The Director will notify the applicant and each person who has submitted written comments or requested notice of that decision. The notice shall include reference to the procedures for contesting the decision. For the purpose of this section, a final permit decision shall mean a final decision to issue, deny, modify, revoke and reissue, or terminate a permit.

    6.12 RESPONSE TO COMMENTS

    (1) At the time that any final permit decision is issued under R317-8-6.11, the Director shall issue a response to comments. This response shall:

    (a) Specify which provisions, if any, of the draft permit have been changed in the final permit decision and the reasons for the change; and

    (b) Briefly describe and respond to all significant comments on the draft permit raised during the public comment period or during any hearing. The response will fully consider all comments resulting from any hearing conducted under this rule.

    (c) The response to the comments shall be available to the public.