R311-203-2. Notification  


Latest version.
  •   (a) The owner or operator of an underground storage tank shall notify the Director whenever:

      (1) new USTs are brought into use;

      (2) the owner or operator changes;

      (3) changes are made to the tank or piping system; and

      (4) release detection, corrosion protection, or spill or overfill prevention systems are installed, changed or upgraded.

      (b) All notifications shall be submitted on the current approved notification form.

      (c) Notifications submitted to meet the requirements of R311-203-2(a)(1) through (4) shall be submitted within 30 days of the completion of the work or the change of ownership.

      (d) To satisfy the requirement of Subsection 19-6-407(1)(c) the certified installer shall:

      (1) complete the appropriate section of the notification form to be submitted by the owner or operator, and ensure that the notification form is submitted by the owner or operator within 30 days of completion of the installation; or

      (2) provide separate notification to the Director within 60 days of the completion of the installation.