R307-415-7f. Permit Revision: Modification  


Latest version.
  • The permit modification procedures described in R307-415-7f shall not affect the requirement that a source obtain an approval order under R307-401 before constructing or modifying a source of air pollution. A modification not subject to the requirements of R307-401 shall not require an approval order in addition to the permit modification as described in this section. A permit modification is any revision to an operating permit that cannot be accomplished under the program's provisions for administrative permit amendments under R307-415-7e. Any permit modification for purposes of the acid rain portion of the permit shall be governed by regulations promulgated under Title IV of the Act.

    (1) Minor permit modification procedures.

    (a) Criteria. Minor permit modification procedures may be used only for those permit modifications that:

    (i) Do not violate any applicable requirement or require an approval order under R307-401;

    (ii) Do not involve significant changes to existing monitoring, reporting, or recordkeeping requirements in the permit;

    (iii) Do not require or change a case-by-case determination of an emission limitation or other standard, or a source-specific determination for temporary sources of ambient impacts, or a visibility or increment analysis;

    (iv) Do not seek to establish or change a permit term or condition for which there is no corresponding underlying applicable requirement and that the source has assumed to avoid an applicable requirement to which the source would otherwise be subject. Such term or condition would include a federally enforceable emissions cap assumed to avoid classification as a modification under any provision of Title I or an alternative emissions limit approved pursuant to regulations promulgated under Section 112(i)(5) of the Act, Early Reduction; and

    (v) Are not modifications under any provision of Title I of the Act.

    (b) Notwithstanding (1)(a)above and (2)(a) below, minor permit modification procedures may be used for permit modifications involving the use of economic incentives, marketable permits, emissions trading, and other similar approaches, to the extent that such minor permit modification procedures are explicitly provided for in the State Implementation Plan or an applicable requirement.

    (c) Application. An application requesting the use of minor permit modification procedures shall meet the requirements of R307-415-5c and shall include all of the following:

    (i) A description of the change, the emissions resulting from the change, and any new applicable requirements that will apply if the change occurs;

    (ii) The source's suggested draft permit;

    (iii) Certification by a responsible official, consistent with R307-415-5d, that the proposed modification meets the criteria for use of minor permit modification procedures and a request that such procedures be used;

    (iv) Completed forms for the director to use to notify EPA and affected States as required under R307-415-8.

    (d) EPA and affected State notification. Within five working days of receipt of a complete permit modification application, the director shall notify EPA and affected States of the requested permit modification. The director promptly shall send any notice required under R307-415-8(2)(b) to EPA.

    (e) Timetable for issuance. The director may not issue a final permit modification until after EPA's 45-day review period or until EPA has notified the director that EPA will not object to issuance of the permit modification, whichever is first. Within 90 days of the director's receipt of an application under minor permit modification procedures or 15 days after the end of EPA's 45-day review period under R307-415-8(3), whichever is later, the director shall:

    (i) Issue the permit modification as proposed;

    (ii) Deny the permit modification application;

    (iii) Determine that the requested modification does not meet the minor permit modification criteria and should be reviewed under the significant modification procedures; or

    (iv) Revise the draft permit modification and transmit to EPA the new proposed permit modification as required by R307-415-8(1).

    (f) Source's ability to make change. A Part 70 source may make the change proposed in its minor permit modification application immediately after it files such application if the source has received an approval order under R307-401 or has met the approval order exemption requirements under R307-413-1 through 6. After the source makes the change allowed by the preceding sentence, and until the director takes any of the actions specified in (1)(e)(i) through (iii) above, the source must comply with both the applicable requirements governing the change and the proposed permit terms and conditions. During this time period, the source need not comply with the existing permit terms and conditions it seeks to modify. However, if the source fails to comply with its proposed permit terms and conditions during this time period, the existing permit terms and conditions it seeks to modify may be enforced against it.

    (g) Permit shield. The permit shield under R307-415-6f shall not extend to minor permit modifications.

    (2) Group processing of minor permit modifications. Consistent with this paragraph, the director may modify the procedure outlined in (1) above to process groups of a source's applications for certain modifications eligible for minor permit modification processing.

    (a) Criteria. Group processing of modifications may be used only for those permit modifications:

    (i) That meet the criteria for minor permit modification procedures under (1)(a) above; and

    (ii) That collectively are below the following threshold level: 10 percent of the emissions allowed by the permit for the emissions unit for which the change is requested, 20 percent of the applicable definition of major source in R307-415-3, or five tons per year, whichever is least.

    (b) Application. An application requesting the use of group processing procedures shall meet the requirements of R307-415-5c and shall include the following:

    (i) A description of the change, the emissions resulting from the change, and any new applicable requirements that will apply if the change occurs.

    (ii) The source's suggested draft permit.

    (iii) Certification by a responsible official, consistent with R307-415-5d, that the proposed modification meets the criteria for use of group processing procedures and a request that such procedures be used.

    (iv) A list of the source's other pending applications awaiting group processing, and a determination of whether the requested modification, aggregated with these other applications, equals or exceeds the threshold set under R307-415-7e(2)(a)(ii).

    (v) Certification, consistent with R307-415-5d, that the source has notified EPA of the proposed modification. Such notification need only contain a brief description of the requested modification.

    (vi) Completed forms for the director to use to notify EPA and affected States as required under R307-415-8.

    (c) EPA and affected State notification. On a quarterly basis or within five business days of receipt of an application demonstrating that the aggregate of a source's pending applications equals or exceeds the threshold level set under (2)(a)(ii) above, whichever is earlier, the director shall notify EPA and affected States of the requested permit modifications. The director shall send any notice required under R307-415-8(2)(b)to EPA.

    (d) Timetable for issuance. The provisions of (1)(e) above shall apply to modifications eligible for group processing, except that the director shall take one of the actions specified in (1)(e)(i) through (iv) above within 180 days of receipt of the application or 15 days after the end of EPA's 45-day review period under R307-415-8(3), whichever is later.

    (e) Source's ability to make change. The provisions of (1)(f) above shall apply to modifications eligible for group processing.

    (f) Permit shield. The provisions of (1)(g) above shall also apply to modifications eligible for group processing.

    (3) Significant modification procedures.

    (a) Criteria. Significant modification procedures shall be used for applications requesting permit modifications that do not qualify as minor permit modifications or as administrative amendments. Every significant change in existing monitoring permit terms or conditions and every relaxation of reporting or recordkeeping permit terms or conditions shall be considered significant. Nothing herein shall be construed to preclude the permittee from making changes consistent with R307-415 that would render existing permit compliance terms and conditions irrelevant.

    (b) Significant permit modifications shall meet all requirements of R307-415, including those for applications, public participation, review by affected States, and review by EPA, as they apply to permit issuance and permit renewal. The director shall complete review on the majority of significant permit modifications within nine months after receipt of a complete application.