R307-401-6. Review Period  


Latest version.
  •   (1) Completeness Determination. Within 30 days after receipt of a notice of intent, or any additional information necessary to the review, the director will advise the applicant of any deficiency in the notice of intent or the information submitted.

      (2) Within 90 days of receipt of a complete application including all the information described in R307- 401-5, the director will

      (a) issue an approval order for the proposed construction, installation, modification, relocation, or establishment pursuant to the requirements of R307-401-8, or

      (b) issue an order prohibiting the proposed construction, installation, modification, relocation or establishment if it is deemed that any part of the proposal is inadequate to meet the applicable requirements of R307.

      (3) The review period under R307-401-6(2) may be extended by up to three 30-day extensions if more time is needed to review the proposal.