R23-33-7. Step Three: Scored Project Review and Revisions Process involving agencies and institutions, the Division of Facilities Construction and Management, BBD and the Board
-
(1) The BBD shall distribute the BBD's preliminary master capital improvement list including categorization, prioritization and scoring, to the Division of Facilities Construction and Management as well as the agencies and institutions for review and comment.
(2) A Construction Budget Estimate (CBE) shall be prepared by the appropriate State employee responsible for preparing a CBE for the particular project using the CBE form provided by the BBD. The CBE shall be based on the Project Scoping Form provided by the BBD.
(3) Each completed CBE form and Project Scoping Form shall be submitted promptly to the BBD and no later than October 15th of the particular year.
(4) The BBD will review each CBE and Project Scoping Form. The BBD will prepare the preliminary scoring along with packet of prioritized capital improvement projects intended for the Board meeting in December. This preliminary scoring and packet shall be submitted by the BBD to the affected agencies or institutions. If there is any disagreement between the BBD and any particular agency or institution, the BBD and the particular agency or institution may endeavor to resolve this matter prior to the packet being sent to the Board. During any such resolution process between the BBD and an agency or institution, the BBD's preliminary scoring and packet may be modified.
(5) The resulting packet and scoring prepared by the BBD under subsection (4) of this Rule, shall be distributed to the Board members as well as the agencies and institutions at least seven days in advance of the December Board meeting.
(6) The Board meeting to review the BBD's capital improvement submittal shall be on or about December 15th of each year.
(7) At the December Board meeting, the Board shall consider input from the BBD, an affected agency or institution as well as interested persons as appropriate.