R23-33-5. Step One: Project Needs Request  


Latest version.
  •   (1) Submission guidelines and formatting requirements shall be approved by the Board prior to submission by the BBD to the agencies and institutions.

      (i) Submission guidelines include the Project Scoping Form which describes in detail the work that needs to be accomplished, statutory requirements, identification of hard and soft costs, submission deadlines and other requirements.

      (ii) The guidelines shall also describe the priority classifications which are in the following ranked order of priority: 1-life safety; 2-critical; 3-necessary; and 4-programatic, as well as the scoring criteria.

      (2) Prior to June of each calendar year, the BBD shall notify agencies and institutions to begin developing their Project Needs Request which includes the agency or institution's prioritized list for the next fiscal year's funding cycles as well as the prioritized scoring process submission guidelines; all to be consistent with applicable law.

      (3) The BBD may provide agencies and institutions with a list of existing Facility Condition Assessment Data ("FCA"), including Risk Management property number, life cycle related to the need, unique FCA project number, and the estimated cost. To the extent the BBD does not provide such information, the agency or institution is required to obtain the information from the FCA database maintained by DFCM and any supplemental information obtained by the agency or institution.

      (4) The Project Needs Request, including the prioritization, shall be submitted by the agencies and institutions to the BBD no later than August 15th immediately following the BBD's notice referred to above.