R23-33-4. General Overview of Process
Latest version.
-
The capital improvement prioritized scoring process consists of five steps as follows:
(1) A Project Needs Request;
(2) Preliminary Project Prioritization and Preliminary Scoring by the BBD;
(3) Preliminary BBD Scored Project Review and Revisions Process involving agencies and institutions, the Division of Facilities Construction and Management, and the BBD;
(4) Submitting the revised Scored List to Board and a Utah State Legislature subcommittee involved with State facility design and construction; and
(5) Review and Final Approval by the Utah State Building Board of the list for submittal to the Utah Legislature.