R131-4-501. Alternative Methods of Construction Contracting Management  


Latest version.
  • (1) Application. This Section contains provisions applicable to the selection of the appropriate type of construction contract management.

    (2) Flexibility. The executive director may devise an appropriate construction contract management method for a particular project that will best meet the needs of the board. The methods outlined in this rule are not an exclusive list.

    (3) Selection. The executive director shall be expected to consider the results achieved on similar projects in the past and the methods used, other appropriate and effective methods, and how a method could be adapted or combined to meet the needs of the state.

    (4) Criteria. Before choosing the construction contracting method, some factors that may be considered include:

    (a) when the facility must be ready for occupancy;

    (b) the type of project, for example, housing, offices, labs, heavy or specialized construction;

    (c) the extent to which the requirements of the occupants are known;

    (d) the location of the project;

    (e) the size, scope, complexity, and economics of the project;

    (f) the amount and type of financing available for the project, including whether the budget is fixed, the source of funding, general or special appropriation, federal assistance moneys, general obligation bonds or revenue bonds;

    (g) the availability, qualification, experience, and available time of assigned State personnel to the project;

    (h) the availability, experience and qualifications of outside consultants and contractors.

    (5) General Descriptions.

    (a) Application of Descriptions. The following descriptions are provided for the more common contracting methods. The methods described are not mutually exclusive and may be combined on a project. These descriptions are not intended to be fixed for all construction projects of the state. In each project, these descriptions may be adapted to fit the circumstances of that project.

    (b) Single Prime Contractor. The single prime contractor method is typified by one business entity acting as a general contractor with the state to complete an entire construction project in accordance with drawings and specifications provided by the state within a defined time period. Generally, the drawings and specifications are prepared by an architectural or engineering firm under contract with the state. Further, while the general contractor may take responsibility for successful completion of the project, much of the work may be performed by specialty contractors with whom the prime contractor has entered into subcontracts.

    (c) Multiple Prime Contractors. Under this method, the board or the board's agent shall contract directly with a number of specialty contractors to complete portions of the project in accordance with the board's drawings and specifications. The board or its agent may have primary responsibility for successful completion of the entire project, or the contracts may provide that one of the multiple prime contractors shall have this responsibility.

    (d) Design-Build. The use of a design build provider is authorized if determined to be used in accordance with this rule. In a design-build project, a business entity shall contract directly with the board to meet requirements described in a set of performance specifications. Both the design and construction responsibilities are assumed by the design-build contractor. This method can include instances where the design-build contractor supplies the site as part of the package.

    (e) Construction Manager. The use of a construction manager, including a construction manager/general contractor, is authorized if determined to be used in accordance with this rule and shall be selected in accordance with R131-4. A construction manager shall be experienced in construction, have the ability to evaluate and to implement drawings and specifications as they affect time, cost, and quality of construction and the ability to coordinate the construction of the project, including the addition of change orders. A contract with a construction manager may be issued early in a project to assist in the development of a cost effective design. The construction manager may be appointed the single prime contractor, or may be required to guarantee that the project will be completed by a specified time, and not to exceed a specified maximum price. The procurement of a construction manager may be based, among other criteria, on proposals for a management fee which is either a lump sum or a percentage of construction costs with a guaranteed maximum cost or, on proposals for a lump sum or guaranteed maximum cost for the construction of the project. The contract with the construction manager may also provide for a sharing of any savings which are achieved below the guaranteed maximum cost. When entering into any subcontract that was not specifically included in the construction manager/general contractor's cost proposal, the construction manager/general contractor shall procure that subcontractor in accordance with R131-4 in the same manner as if the subcontract work was procured directly by the board.

    (f) Sequential Design and Construction. Sequential design and construction is a method whereby design of substantially the entire structure is completed prior to beginning the construction process.

    (g) Phased Design and Construction. Phased design and construction is a method whereby construction is begun when appropriate portions have been designed but before design of the entire structure has been completed. This method is also known as fast track construction.

    (h) Design Assist Contracting. Design assist contacting may be used when it is determined by the executive director that a contractor (including a particular subcontractor trade) is needed subject to the following:

    (i) it is determined that the design assist contractor (DAC) has a unique knowledge of a material or product that warrants the interaction of the DAC early on with the designer;

    (ii) the DAC will be providing construction estimates, details and documents as well as the construction or installation of materials or products into the project;

    (iii) the DAC is selected through a competitive sealed proposal process where qualifications are the main criteria for selection;

    (iv) the DAC will provide information to the executive director and the designer of the project as needed to define the scope of the work for a fee; and

    (v) a contract may be entered with a DAC only when the proposed cost for the work is equal to or less than the budget established by the board for the project, provided that the board may increase the budget, the board/executive director may use the information provided by the DAC and initiate a procurement process for the construction or installation; or the board/executive director may reduce the scope of the work.