R930-5-9. Funding Authorization and Apportionment of Cost for Section 130 Crossing Projects  


Latest version.
  • (1) Funding Authorization.

    (a) Section 130 Crossing Projects:

    (i) Costs associated with a FHWA authorized and approved program are eligible for federal participation. Eligible costs incurred in an approved program prior to authorization by FHWA are not reimbursable, but may be included as part of the Railroad share of the project cost where such a share is required. Eligible costs include, but are not limited to cost associated with environmental clearance, Preliminary Engineering, and right-of-way acquisition.

    (ii) Prior to FHWA issuing its authorization to advertise the construction of a Crossing project, the Crossing project must receive environmental clearance; the plans, specifications and estimates must be approved by FHWA; and any proposed agreement between the Railroad and the Department must be reviewed and approved by FHWA, as per FHWA's stewardship agreement with the Department.

    (b) Non-Section 130 Crossing Projects:

    (i) The Department will consider requests for funding of non-Section 130 Crossing Projects as part of its regular STIP evaluation and approval process.

    (2) Apportionment of Costs.

    (a) Section 130 Crossing Projects:

    (i) Apportionment of costs for installation, maintenance, and reconstruction of safety related improvements at a Crossing shall be in accordance with 23 CFR 646 and Section 54-4-15.

    (ii) When a Highway Authority widens a Highway, the Highway Authority shall fund all improvements including, but not limited to Passive Warning Devices, Active Warning Devices, Crossing material, and other improvements as ordered by the Department in consultation with the Diagnostic Team.

    (iii) The Department will evaluate each Crossing project to determine the extent to which, if any, the Crossing projects benefits the respective parties. If a Crossing project is determined not to benefit a party, the party will not be required to participate in the funding.

    (b) Non-Section 130 Crossing Projects.

    (i) The Department will consider requests for funding of non-Section 130 Crossing Projects as part of its regular STIP evaluation and approval process.