R916-1-6. Award of Contracts  


Latest version.
  • (1) The department shall award the contract to the lowest responsible and qualified bidder.

    (2) When all bids received exceed the engineer's estimate by more than 10%, the department reserves the right to either accept the low bid or to reject all bids.

    (3) The award, if made, shall be within 30 days after the opening of proposals. The department may, subject to approval of the successful bidder, withhold the award beyond the 30 day time frame. After 30 days, if no award has been made, the contractor may withdraw their proposal without liability.

    (4) The successful bidder shall be notified, by mail using the address shown on their proposal, that they have been awarded the contract.

    (5) The department reserves the right to cancel the award of any contract at any time before the execution of the contract by all parties with no liability against the department.