R81-6-1. Application  


Latest version.
  • (1) No application will be included on the agenda of a monthly commission meeting for consideration for issuance of a special use permit until:

    (a) The applicant has first met all requirements of Sections 32B-1-304 (qualifications to hold the permit), and 32B-10-202 and -205 (submission of a completed application, payment of application and permit fees if required for the type of permit being sought, statement of purpose for which the applicant applies for the permit, types of alcoholic product the person intends to use under the permit, written consent of local authority, a bond if required, and a floor plan if required; and

    (b) the department has inspected the restaurant premise.

    (2)(a) All application requirements of Subsection (1)(a) must be filed with the department no later than the 10th day of the month in order for the application to be included on that month's commission meeting agenda unless the 10th day of the month is a Saturday, Sunday, or state or federal holiday, in which case all application requirements of Subsection (1)(a) must be filed on the next business day after the 10th day of the month.

    (b) An incomplete application will be returned to the applicant.

    (c) A completed application filed after the deadline in Subsection (2)(a) will not be considered by the commission that month, but will be included on the agenda of the commission meeting the following month.