R746-313-6. Inquiries about Electric Service Reliability  


Latest version.
  • (1) A customer may request a report from its electric company about the reliability of the electric service provided to the customer's own meter which the electric company must provide at no cost within 20 business days of the request. If a customer requests one or more additional reliability reports for the same meter within one year of the date of the first request, the electric company may charge the customer the cost of preparing the report(s).

    (2) For an electric company whose governing authority is the commission, the report to the customer must include:

    (a) The name of the customer;

    (b) The date of the request;

    (c) The address where the meter is installed;

    (d) The meter identification number;

    (e) The general identification of the equipment serving the customer; and

    (f) A chronological listing of interruptions to the customer including all associated interruption data required by R746-313-5(2) covering at least the 36 months preceding the date of the request, if available. If 36 months of data are not available, the chronological listing must include all available data.

    (3) For an electric company whose governing authority is not the commission, the report to the customer must include:

    (a) The name of the customer;

    (b) The date of the request;

    (c) The address where the meter is installed;

    (d) The meter identification number;

    (e) The general identification of the equipment serving the customer; and

    (f) A chronological listing of interruptions on the feeder serving the customer's meter including all interruption data required by R746-313-5(2) covering at least the 12 months preceding the date of the request. If 12 months of data are not available, the chronological listing must include all available data.

    (4) Other than those inquiries specified in R746-313-6(1), each electric company must have a written policy for consistent treatment of all other inquiries pertaining to electric reliability. At a minimum, the electric company must provide to the inquiring party, by electronic means, the electric company's most-recently filed report on electric service reliability required by R764-313-7.