Utah Administrative Code (Current through November 1, 2019) |
R746. Public Service Commission, Administration |
R746-312. Electrical Interconnection |
R746-312-17. Interconnection-related Agreements
-
(1) Contents of Standard Interconnection Agreement. All standard form interconnection agreements shall, at a minimum, contain the following:
(a) a requirement that the generating facility must be inspected by a local building code official prior to its operation in parallel with the public utility to ensure compliance with applicable local codes.
(b) provisions that permit the public utility to inspect interconnection customer's generating facility and its component equipment, and the documents necessary to ensure compliance with this rule. The customer shall notify the public utility as required by this rule prior to initially placing customer equipment and protective apparatus in service, and the public utility shall have the right to have personnel present on the in-service date. If the generating system is subsequently modified in order to increase its gross power rating, the customer must notify the public utility by submitting a new application specifying the modifications in accordance with the level of review required for the application.
(c) a provision that the customer is responsible for protecting the generating equipment, inverters, protective devices, and other system components from damage from the normal and abnormal conditions and operations that occur on the public utility system in delivering and restoring power; and is responsible for ensuring that the generating facility equipment is inspected, maintained, and tested in accordance with the manufacturer's instructions to ensure that it is operating correctly and safely.
(d) a provision that the customer shall hold harmless and indemnify the public utility for all loss to third parties resulting from the operation of the generating facility, except when the loss occurs due to the negligent actions of the public utility and a provision that the public utility shall hold harmless and indemnify the customer for all loss to third parties resulting from the operation of the public utility's system, except when the loss occurs due to the negligent actions of the customer.
(e) Insurance:
(i) If an interconnection customer whose generating facility is no greater than two megawatts in size complies with the provisions of the interconnection request approval, interconnection agreement, and standards identified in Section 54-15-106, a public utility may not require that interconnection customer to purchase additional liability insurance.
(ii) all other interconnection customers are required to obtain prudent amounts of general liability insurance in an amount sufficient to protect other parties from any loss, cost, claim, injury, liability, or expense, including reasonable attorney fees, relating to or arising from any act or omission in its performance of the provisions of the this rule or the interconnection agreement. Neither party may seek redress from the other party in an amount greater than the amount of direct damage actually incurred. An interconnection customer of sufficient credit-worthiness may propose to self-insure for such liabilities and such proposal shall not be unreasonably rejected.
(f) identification of any fees or charges approved pursuant to this rule or applicable law.