R649-3-4. Permitting of Wells to be Drilled, Deepened or Plugged-Back  


Latest version.
  • 1. Prior to the commencement of drilling, deepening or plugging back of any well, exploratory drilling such as core holes and stratigraphic test holes, or any surface disturbance associated with such activity, the operator shall submit Form 3, Application for Permit to Drill, Deepen, or Plug Back and obtain approval. Approval shall be given by the division if it appears that the contemplated location and operations are not in violation of any rule or order of the board for drilling a well.

    2. The following information shall be included as part of the complete Application for Permit to Drill, Deepen, or Plug Back.

    2.1. The telephone number of the person to contact if additional information is needed.

    2.2. Proper identification of the lease as state, federal, Indian, or fee.

    2.3. Proper identification of the unit, if the well is located within a unit.

    2.4. A plat or map, preferably on a scale of one inch equals 1,000 feet, prepared by a licensed surveyor or engineer, that shows the proposed well location. For directional wells, both surface and bottomhole locations should be marked.

    2.5. A copy of the Division of Water Rights approval or the identifying number of the approval for use of water at the drilling site.

    2.6. A drilling program containing the following information shall also be submitted as part of a complete APD.

    2.6.1. The estimated tops of important geologic markers.

    2.6.2. The estimated depths at which the top and the bottom of anticipated water, oil, gas, or other mineral-bearing formations are expected to be encountered, and the owner's or operator's plans for protecting such resources.

    2.6.3. The owner's or operator's minimum specifications for pressure control equipment to be used and a schematic diagram thereof showing sizes, pressure ratings or API series, proposed testing procedures and testing frequency.

    2.6.4. Any supplementary information more completely describing the drilling equipment and casing program as required by Form 3, Application for Permit to Drill, Deepen, or Plug Back.

    2.6.5. The type and characteristics of the proposed circulating medium or mediums to be employed in drilling, the quantities and types of mud and weighting material to be maintained, and the monitoring equipment to be used on the mud system.

    2.6.6. The anticipated type and amount of testing, logging, and coring.

    2.6.7. The expected bottomhole pressure and any anticipated abnormal pressures or temperatures or potential hazards, such as hydrogen sulfide, H2S rules are found in R649-3-12 expected to be encountered, along with contingency plans for mitigating such identified hazards.

    2.6.8. Any other facets of the proposed operation that the lessee or operator desires to point out for the division's consideration of the application.

    2.6.9. If an Application for Permit to Drill, Deepen, or Plug Back is for a proposed horizontal well, a horizontal well diagram clearly showing the well bore path from the surface through the terminus of the lateral shall be submitted.

    2.7. Form 5, Designation of Agent or Operator shall be filed when the operator is a person other than the owner.

    2.8. If located on State or Fee surface, an APD will not be approved until an Onsite Predrill Evaluation is performed as outlined in R649-3-18.

    3. Two legible copies, carbon or otherwise, of the APD filed with the appropriate federal agency may be used in lieu of the forms prescribed by the board.

    4. Approval of the APD shall be valid for a period of 12 months from the date of such approval. Upon approval of an APD, a well will be assigned an API number by the division. The API number should be used to identify the permitted well in all future correspondence with the division.

    5. If a change of location or drilling program is desired, an amended APD shall be filed with the division and its approval obtained. If the new location is at an authorized location in the approved drilling unit, or the change in drilling program complies with the rules for that area, the change may be approved verbally or by telegraph. Within five days after obtaining verbal or telegraphic authorization, the operator shall file a written change application with the division.

    6. After a well has been completed or plugged and abandoned, it shall not be reentered without the operator first submitting a new APD and obtaining the division's approval. Approval shall be given if it appears that a bond has been furnished or waived, as required by R649-3-1, Bonding, and the contemplated work is not in violation of any rule or order of the board.

    7. An operator or owner who applies for an APD in an area not subject to a special order of the board establishing drilling units, may contemporaneously or subsequently file a Request for Agency Action to establish drilling units for an area not to exceed the area reasonably projected by the operator or owner to be underlaid by the targeted reservoir.

    8. An APD for a well within the area covered by a proper Request for Agency Action that has been filed by an interested person, or the division or the board on its own motion, for the establishment of drilling units or the revision of existing drilling units for the spacing of wells shall be held in abeyance by the division until such time as the matter has been noticed, fully heard and determined.

    9. An exception to R649-3-4-8 shall be made and a permit shall be issued by the division if an owner or operator files a sworn statement demonstrating to the division's satisfaction that on and after the date the Request for Agency Action requesting the establishment of drilling units was filed, or the action of the division or board was taken; and

    9.1. The owner or operator has the right or obligation under the terms of an existing contract to drill the requested well; or

    9.2. The owner or operator has a leasehold estate or right to acquire a leasehold estate under a contract that will be terminated unless he is permitted to commence the drilling of the required well before the matter can be fully heard and determined by the board.