R315-319-106. Recordkeeping, Notification, and Posting of Information to the Internet Notification Requirements  


Latest version.
  •   (a) The notifications required under Subsections R315-319-106(e) through (i) shall be sent to the Director before the close of business on the day the notification is required to be completed. For purposes of Section R315-319-106, before the close of business means the notification shall be postmarked or sent by electronic mail (email). If a notification deadline falls on a weekend or federal holiday, the notification deadline is automatically extended to the next business day.

      (b) Reserved

      (c) Notifications may be combined as long as the deadline requirement for each notification is met.

      (d) Unless otherwise required in Section R315-319-106, the notifications specified in Section R315-319-106 shall be sent to the Director within 30 days of placing in the operating record the information required by Subsection R315-319-105.

      (e) Location restrictions. The owner or operator of a CCR unit subject to the requirements of Sections R315-319-50 through 107 shall notify the Director that each demonstration specified under Subsection R315-319-105(e) has been placed in the operating record and on the owner or operator's publicly accessible internet site.

      (f) Design criteria. The owner or operator of a CCR unit subject to Sections R315-319-50 through 107 shall notify the Director when information has been placed in the operating record and on the owner or operator's publicly accessible Internet site. The owner or operator shall:

      (1) Within 60 days of commencing construction of a new CCR unit, provide notification of the availability of the design certification specified under Subsection R315-319-105(f)(1) or (3). If the owner or operator of the CCR unit elects to install an alternative composite liner, the owner or operator shall also submit to the Director a copy of the alternative composite liner design.

      (2) No later than the date of initial receipt of CCR by a new CCR unit, provide notification of the availability of the construction certification specified under Subsection R315-319-105(f)(1) or (3).

      (3) Provide notification of the availability of the documentation of liner type specified under Subsection R315-319-105(f)(2).

      (4) Provide notification of the availability of the initial and periodic hazard potential classification assessments specified under Subsection R315-319-105(f)(5).

      (5) Provide notification of the availability of emergency action plan (EAP), and any revisions of the EAP, specified under Subsection R315-319-105(f)(6).

      (6) Provide notification of the availability of documentation prepared by the owner or operator recording the annual face-to-face meeting or exercise between representatives of the owner or operator of the CCR unit and the local emergency responders specified under Subsection R315-319-105(f)(7).

      (7) Provide notification of documentation prepared by the owner or operator recording all activations of the emergency action plan specified under Subsection R315-319-105(f)(8).

      (8) Provide notification of the availability of the history of construction, and any revision of it, specified under Subsection R315-319-105(f)(9).

      (9) Provide notification of the availability of the initial and periodic structural stability assessments specified under Subsection R315-319-105(f)(10).

      (10) Provide notification of the availability of the documentation detailing the corrective measures taken to remedy the deficiency or release specified under Subsection R315-319-105(f)(11).

      (11) Provide notification of the availability of the initial and periodic safety factor assessments specified under Subsection R315-319-105(f)(12).

      (12) Provide notification of the availability of the design and construction plans, and any revision of them, specified under Subsection R315-319-105(f)(13).

      (g) Operating criteria. The owner or operator of a CCR unit subject to Sections R315-319-50 through 107 shall notify the Director when information has been placed in the operating record and on the owner or operator's publicly accessible Internet site. The owner or operator shall:

      (1) Provide notification of the availability of the CCR fugitive dust control plan, or any subsequent amendment of the plan, specified under Subsection R315-319-105(g)(1).

      (2) Provide notification of the availability of the annual CCR fugitive dust control report specified under Subsection R315-319-105(g)(2).

      (3) Provide notification of the availability of the initial and periodic run-on and run-off control system plans specified under Subsection R315-319-105(g)(3).

      (4) Provide notification of the availability of the initial and periodic inflow design flood control system plans specified under Subsection R315-319-105(g)(4).

      (5) Provide notification of the availability of the periodic inspection reports specified under Subsection R315-319-105(g)(6).

      (6) Provide notification of the availability of the documentation detailing the corrective measures taken to remedy the deficiency or release specified under Subsection R315-319-105(g)(7).

      (7) Provide notification of the availability of the periodic inspection reports specified under Subsection R315-319-105(g)(9).

      (h) Groundwater monitoring and corrective action. The owner or operator of a CCR unit subject to Sections R315-319-50 through 107 shall notify the Director when information has been placed in the operating record and on the owner or operator's publicly accessible Internet site. The owner or operator shall:

      (1) Provide notification of the availability of the annual groundwater monitoring and corrective action report specified under Subsection R315-319-105(h)(1).

      (2) Provide notification of the availability of the groundwater monitoring system certification specified under Subsection R315-319-105(h)(3).

      (3) Provide notification of the availability of the selection of a statistical method certification specified under Subsection R315-319-105(h)(4).

      (4) Provide notification that an assessment monitoring programs has been established specified under Subsection R315-319-105(h)(5).

      (5) Provide notification that the CCR unit is returning to a detection monitoring program specified under Subsection R315-319-105(h)(7).

      (6) Provide notification that one or more constituents in appendix IV to Rule R315-319 have been detected at statistically significant levels above the groundwater protection standard and the notifications to land owners specified under Subsection R315-319-105(h)(8).

      (7) Provide notification that an assessment of corrective measures has been initiated specified under Subsection R315-319-105(h)(9).

      (8) Provide notification of the availability of assessment of corrective measures specified under Subsection R315-319-105(h)(10).

      (9) Provide notification of the availability of the semiannual report describing the progress in selecting and designing the remedy and the selection of remedy report specified under Subsection R315-319-105(h)(12).

      (10) Provide notification of the completion of the remedy specified under Subsection R315-319-105(h)(13).

      (i) Closure and post-closure care. The owner or operator of a CCR unit subject to Sections R315-319-50 through 107 shall notify the Director when information has been placed in the operating record and on the owner or operator's publicly accessible Internet site. The owner or operator shall:

      (1) Provide notification of the intent to initiate closure of the CCR unit specified under Subsection R315-319-105(i)(1).

      (2) Provide notification of the availability of the annual progress reports of closure implementation specified under Subsection R315-319-105(i)(2).

      (3) Provide notification of closure completion specified under Subsection R315-319-105(i)(3).

      (4) Provide notification of the availability of the written closure plan, and any amendment of the plan, specified under Subsection R315-319-105(i)(4).

      (5) Provide notification of the availability of the demonstration(s) for a time extension for initiating closure specified under Subsection R315-319-105(i)(5).

      (6) Provide notification of the availability of the demonstration(s) for a time extension for completing closure specified under Subsection R315-319-105(i)(6).

      (7) Provide notification of intent to close a CCR unit specified under Subsection R315-319-105(i)(7).

      (8) Provide notification of completion of closure of a CCR unit specified under Subsection R315-319-105(i)(8).

      (9) Provide notification of the deed notation as required by Subsection R315-319-105(i)(9).

      (10) Provide notification of intent to comply with the alternative closure requirements specified under Subsection R315-319-105(i)(10).

      (11) The annual progress reports under the alternative closure requirements as required by Subsection R315-319-105(i)(11).

      (12) Provide notification of the availability of the written post-closure plan, and any amendment of the plan, specified under Subsection R315-319-105(i)(12).

      (13) Provide notification of completion of post-closure care specified under Subsection R315-319-105(i)(13).

      (j) Retrofit criteria. The owner or operator of a CCR unit subject to Sections R315-319-50 through 107 shall notify the Director when information has been placed in the operating record and on the owner or operator's publicly accessible Internet site. The owner or operator shall:

      (1) Provide notification of the availability of the written retrofit plan, and any amendment of the plan, specified under Subsection R315-319-105(j)(1).

      (2) Provide notification of intent to comply with the alternative retrofit requirements specified under Subsection R315-319-105(j)(2).

      (3) The annual progress reports under the alternative retrofit requirements as required by Subsection R315-319-105(j)(3).

      (4) Provide notification of the availability of the demonstration(s) for a time extension for completing retrofit activities specified under Subsection R315-319-105(j)(4).

      (5) Provide notification of intent to initiate retrofit of a CCR unit specified under Subsection R315-319-105(j)(5).

      (6) Provide notification of completion of retrofit activities specified under Subsection R315-319-105(j)(6).