R23-3-4. Authorization of Programs  


Latest version.
  •   (1) An agency is required to receive approval from the Board before the agency begins programming for a new facility that requires legislative approval under Subsection 63A-5-104(3).

      (2) When requesting Board approval, the agency shall justify the need for initiating the programming process at that point in time and also address the level of support for funding the project soon after the program will be completed.

      (3) The Board may approve the programming of a new facility before the Legislature makes an appropriation for the new facility under Subsection 63A-5-104(8)(a). When the program is funded by the agency, programming funds may be reimbursed from an appropriation if, at a later time, the Legislature funds the programming.