R23-1-616. Bids Over Budget  


Latest version.
  •   (1) In the event all bids for a construction project exceed available funds as certified by the appropriate fiscal officer, and the low responsive and responsible bid does not exceed those funds by more than 5%, the Director may, where time or economic considerations preclude resolicitation of work of a reduced scope, negotiate an adjustment of the bid price, including changes in the bid requirements, with the low responsive and responsible bidder in order to bring the bid within the amount of available funds.

      (2) As an alternative to the procedure authorized in Subsection (1), when all bids for a construction project exceed available funds as certified by the Director, and the Director finds that due to time or economic considerations the re-solicitation of a reduced scope of work would not be in the interest of the state, the Director may negotiate an adjustment in the bid price using one of the following methods:

      (a) reducing the scope of work in specific subcontract areas and supervising the re-bid of those subcontracts by the low responsive and responsible bidder;

      (b) negotiating with the low responsive and responsible bidder for a reduction in scope and cost with the value of those reductions validated in accordance with Section R23-1-50; or

      (c) revising the contract documents and soliciting new bids only from bidders who submitted a responsive bid on the original solicitation. This re-solicitation may have a shorter bid response time than otherwise required.

      (3) The use of one of the alternative procedures provided for in this subsection (2) must provide for the fair and equitable treatment of bidders.

      (4) The Director's written determination, including a brief explanation of the basis for the decision shall be included in the contact file.

      (5) This Rule does not restrict in any way, the right of the Director to use any emergency or sole source procurement provisions, or any other applicable provisions of State law or rule which may be used to award the construction project.