R23-1-1306. Special Provisions Regarding Construction Manager/General Contractor  


Latest version.
  •   (1) In the selection of a construction manager/general contractor, a standard procurement process as defined in Section 63G-6a-103 may be used or an exception allowed under Part 8 of the Utah Procurement Code.

      (2) When the CM/GC enters into any subcontract that was not specifically included in the construction manager/general contractor's cost proposal, the CM/GC shall procure the subcontractor(s) by using a standard procurement process as defined in Section 63G-6a-103 of the Utah Procurement Code or an exception to the requirement to use a standard procurement process, described in Part 8 of the Utah Procurement Code.