(Amendment)
DAR File No.: 39246
Filed: 03/30/2015 09:07:09 AMRULE ANALYSIS
Purpose of the rule or reason for the change:
The purpose of this proposed rule change is to provide utility customers who rely on life-supporting equipment the same protections they currently receive with respect to termination of utility service, while at the same time reducing the regulatory burden on both the utility and on the Division of Public Utilities. This proposed rule change is designed to provide affected customers with the same right to request a hearing while eliminating some of the paperwork and filing requirements.
Summary of the rule or change:
Changing the current process under which a public utility must petition the Public Service Commission for approval to terminate utility service in some instances, this proposed rule change eliminates the requirement for the utility to petition for approval. Instead, the proposed rule change increases the disclosures the public utility is required to include in a notice of proposed termination involving life-supporting equipment (clearly and plainly informing the customer of the customer's rights), and provides to the affected customer a right to request an expedited hearing within the same time frame currently allowed to protest a petition for approval.
State statutory or constitutional authorization for this rule:
Anticipated cost or savings to:
the state budget:
The proposed rule change should result in a slight decrease in filing requirements that apply to the Division of Public Utilities with a negligible cost savings.
local governments:
This rule does not apply to public utilities operated by municipalities, and local governments will not be impacted by this proposed rule change.
small businesses:
The proposed rule change should result in a slight decrease in filing requirements that apply to a public utility with a negligible cost savings.
persons other than small businesses, businesses, or local governmental entities:
The proposed rule change should result in a slight decrease in filing requirements that apply to a public utility with a negligible cost savings.
Compliance costs for affected persons:
Public utility customers who use life-supporting equipment will continue to receive the same protections with respect to termination of public utility service, and will retain the option to request an expedited hearing in the same way they currently may protest a proposed termination of utility service.
Comments by the department head on the fiscal impact the rule may have on businesses:
This proposed rule change will protect the current rights of utility customers who rely on life-supporting equipment while reducing the filing and paperwork requirements that currently apply to the public utility and to the Division of Public Utilities. Negligible cost savings should result.
Ron Allen, Chairman
The full text of this rule may be inspected, during regular business hours, at the Division of Administrative Rules, or at:
Public Service Commission
Administration
HEBER M WELLS BLDG
160 E 300 S
SALT LAKE CITY, UT 84111-2316Direct questions regarding this rule to:
- Sheri Bintz at the above address, by phone at 801-530-6714, by FAX at 801-530-6796, or by Internet E-mail at sbintz@utah.gov
- Jordan White at the above address, by phone at 801-530-6712, by FAX at , or by Internet E-mail at jordanwhite@utah.gov
Interested persons may present their views on this rule by submitting written comments to the address above no later than 5:00 p.m. on:
05/15/2015
This rule may become effective on:
05/22/2015
Authorized by:
Jordan White, Legal Counsel
RULE TEXT
R746. Public Service Commission, Administration.
R746-200. Residential Utility Service Rules for Electric, Gas, Water, and Sewer Utilities.
R746-200-7. Termination of Service.
A. Definitions. As used in this section (R746-200-7):
1. "Licensed medical provider" means a medical provider:
a. who holds a current and active medical license under Utah Code Title 58; and
b. whose scope of practice authorizes the medical provider to diagnose the condition described by the medical provider under this rule[
,].2. "Life-supporting equipment" means life-supporting medical equipment:
a. with normal operation that requires continuation of public utility service; and
b. used by an individual who would require immediate assistance from medical personnel to sustain life if the life supporting equipment ceased normal operations.
3. "Life-supporting equipment statement" means a written statement:
a. signed by the licensed medical provider for the account holder or resident who utilizes life-supporting equipment; and
b. including:
i. a description of the medical need of the account holder or resident who utilizes life-supporting equipment;
ii. the account holder's name and address;
iii. name of resident using life-supporting equipment and relationship to account holder, if different than account holder;
iv. the health infirmity and expected duration;
v. identification of the life-support equipment that requires the utility's service;
vi. a determination by the licensed medical provider that immediate assistance from medical personnel to sustain life would be required if the life supporting equipment ceased normal operations; and
vii. the name and contact information of the licensed medical provider for the resident who utilizes life-supporting equipment,
4. "Serious illness or infirmity statement" means a written statement:
a. signed by a licensed medical provider;
b. written on:
i. a form obtained from the public utility; or
ii. the licensed medical provider's letterhead stationary;
c. legibly describing:
i. a diagnosed medical condition under which termination of utility service will injure the person's health or aggravate the person's illness; and
ii. the anticipated duration of the diagnosed medical condition.
B. Delinquent Account --
1. A residential utility service bill [
which]that has remained unpaid beyond the statement due date is a delinquent account.2. When an account is a delinquent account, a public utility, before termination of service, shall issue a written late notice to inform the account holder of the delinquent status. A late notice or reminder notice must include the following information:
a. A statement that the account is a delinquent account and should be paid promptly;
b. A statement that the account holder should communicate with the public utility's collection department, by calling the company, if [
he]the account holder has a question concerning the account;c. A statement of the delinquent account balance, using a term such as "delinquent account balance."
3. When the account holder responds to a late notice or reminder notice the public utility's collections personnel shall investigate disputed issues and shall try to resolve the issues by negotiation. During this investigation and negotiation no other action shall be taken to disconnect the residential utility service if the account holder pays the undisputed portion of the account subject to the utility's right to terminate utility service pursuant to R746-200-7(F), Termination of Service Without Notice.
4. A copy of the "Statement of Customer Rights and Responsibilities" referred to in Subsection R746-200-1(G) of these rules shall be issued to the account holder with the first notice of impending service disconnection.
C. Reasons for Termination of Service --
1. Residential utility service may be terminated for the following reasons:
a. Nonpayment of a delinquent account;
b. Nonpayment of a deposit when required;
c. Failure to comply with the terms of a deferred payment agreement or Commission order;
d. Unauthorized use of, or diversion of, residential utility service or tampering with wires, pipes, meters, or other equipment;
e. Subterfuge or deliberately furnishing false information; or
f. Failure to provide access to meter during the regular route visit to the premises following proper notification and opportunity to make arrangements in accordance with R746-200-4(B), Estimated Billing, Subsection (2).
2. The following shall be insufficient grounds for termination of service:
a. A delinquent account, accrued before a divorce or separate maintenance action in the courts, in the name of a former spouse, cannot be the basis for termination of the current account holder's service;
b. Cohabitation of a current account holder with a delinquent account holder whose utility service was previously terminated for non-payment, unless the current and delinquent account holders also cohabited while the delinquent account holder received the utility's service, whether the service was received at the current account holder's present address or another address;
c. When the delinquent account balance is less than $25.00, unless no payment has been made for two months;
d. Failure to pay an amount in bona fide dispute before the Commission;
e. Payment delinquency for third party services billed by the regulated utility company, unless prior approval is obtained from the Commission.
D. Restrictions upon Termination of Service -- Medical Reasons --
1. Serious Illness or Infirmity. If a public utility receives a serious illness or infirmity statement:
a. the public utility shall continue or restore residential utility service for the period set forth in the statement or one month, whichever is less;
b. the public utility is not required to provide the continuation or restoration described in R746-200-7.D.1.a. more than two times to an individual customer or residence during the same calendar year; and
c. the account holder is liable for the cost of residential utility service during the period of continued or restored service.
2. Life-Supporting Equipment.
a. After receiving a life-supporting equipment statement, the public utility:
i. shall mark and identify applicable meter boxes where the life-supporting equipment is used;
ii. may not terminate service to the residence unless the public utility has [
obtained prior approval from the Commission]complied with this Subsection (R746-200-7.D.2); andiii. may request annual verification from the licensed medical provider of the life-supporting equipment.
b. A public utility may [
petition the Commission for authorization to]terminate service on an account where the public utility has received a life-supporting equipment statement and the related medical provider verification, if:i. [
if]the account is in default;ii. [
if]the public utility has:AA. followed R746-200-5 on offering a deferred payment agreement; or
BB. if R746-200-5 does not apply, allowed the customer one month to enter into a deferred payment agreement that may last up to 12 months;[
and]iii. [
by filing its petition with the Commission and providing a copy to the Division.]after complying with R746-200-7.D.2.b.ii, the public utility has provided to the customer a written notice of proposed termination of service that:AA. clearly and plainly informs the customer of the customer's rights under R746-200-7.D.2 and of the customer's right to an expedited complaint hearing under R746-200-8.E.; and
BB. complies with R746-200-7.G.1;
iv. the public utility has provided to the customer a 48 hour notice of termination of utility service that complies with R746-200-7.G.2; and
v. the public utility has complied with all other applicable provisions of R746-200-7.
[
c. A petition for authorization to terminate service shall contain:i. the public utility's written request to the Commission to terminate service;ii. the life-supporting equipment statement;iii. the information provided to the public utility by the licensed medical provider;iv. a copy of a letter sent to the account holder and, if appropriate, to a third party, notifying the account holder of the account holder's right to file a protest with the Commission within 10 days; andv. an affidavit verifying the public utility provided the account holder and, if appropriate, a third party, the information required by this rule.d. Within two business days after receiving a petition for authorization to terminate service, the Division shall:i. notify the account holder by regular and certified mail that the utility is requesting authorization from the Commission to terminate service; andii. instruct the account holder to contact the utility for further information.e. After receiving a petition for authorization to terminate service, the Commission may:i. schedule an expedited hearing if a protest is received within 10 days; orii. issue an order authorizing termination of service if the requirements of this rule have been satisfied.f. If a public utility receives authorization to terminate service, the public utility shall provide a 48 hour notice of termination to the customer consistent with R746-200-7.G.2.][
g.]c. The account holder is liable for the cost of residential utility service during the period of service, including throughout all proceedings related to life-supporting equipment.E. Payments from the Home Energy Assistance Target (HEAT) Program -- Suppliers may not discontinue utility service to a low-income household for at least 30 days after receiving utility payment or verification of utility payment from the HEAT Program on behalf of the low-income household.
F. Termination of Service Without Notice -- Any provision contained in these rules notwithstanding, a public utility may terminate residential utility service without notice when, in its judgment, a clear emergency or serious health or safety hazard exists for so long as the conditions exist, or when there is unauthorized use or diversion of residential utility service or tampering with wires, pipes, meters, or other equipment owned by the utility. The utility shall immediately try to notify the customer of the termination of service and the reasons therefor.
G. Notice of Proposed Termination of Service --
1. At least 10 calendar days before a proposed termination of residential utility service, or at least 30 calendar days before a proposed termination if the residential utility service customer has provided to the public utility a life-supporting equipment statement, a public utility shall give written notice of disconnection for nonpayment to the account holder. The 10-day or 30-day time period is computed from the date the [
bill]notice is postmarked. The notice shall be given by first class mail or delivery to the premises and shall contain a summary of the following information:a. a Statement of Customer Rights and Responsibilities under existing state law and Commission rules;
b. the Commission-approved policy on termination of service for that utility;
c. the availability of deferred payment agreements and sources of possible financial assistance including but not limited to state and federal energy assistance programs;
d. informal and formal procedures to dispute bills and to appeal adverse decisions, including the Commission's address, website, and telephone number;
e. specific steps, printed in a conspicuous fashion, that may be taken by the consumer to avoid termination of service;
f. the date on which payment arrangements must be made to avoid termination of service; and
g. subject to the provision of Subsection R746-200-1(E), Customer Information, a conspicuous statement, in Spanish, that the notice is a termination of service notice and that the utility has a Spanish edition of its customer information pamphlet and whether it has personnel available during regular business hours to communicate with Spanish-speaking customers.
2. At least 48 hours before termination of service is scheduled, the utility shall make good faith efforts to notify the account holder or an adult member of the household, by mail, by telephone or by a personal visit to the residence. If personal notification has not been made either directly by the utility or by the customer in response to a mailed notice, the utility shall leave a written termination of service notice at the residence. Personal notification, such as a visit to the residence or telephone conversation with the customer, is required only during the winter months, October 1 through March 31. Other months of the year, the mailed 48-hour notice can be the final notice before the termination of service.
If termination of service is not accomplished within 15 business days following the 48-hour notice, the utility company will follow the same procedures for another 48-hour notice.
3. A public utility shall send duplicate copies of 10-day or 30-day termination of service notices to a third party designated by the account holder and shall make reasonable efforts to personally contact the third party designated by the account holder before termination of service occurs, if the third party resides within its service area. A utility shall inform its account holders of the third-party notification procedure at the time of application for service and at least once each year.
4. In rental property situations where the tenant is not the account holder and that fact is known to the utility, the utility shall post a notice of proposed termination of service on the premises in a conspicuous place and shall make reasonable efforts to give actual notice to the occupants by personal visits or other appropriate means at least five calendar days before the proposed termination of service. The posted notice shall contain the information listed in Subsection R746-200-7(G)(1). This notice provision applies to residential premises when the account holder has requested termination of service or the account holder has a delinquent bill. If nonpayment is the basis for the termination of service, the utility shall also advise the tenants that they may continue to receive utility service for an additional 30 days by paying the charges due for the 30-day period just past.
H. Termination of Service -- Upon expiration of the notice of proposed termination of service, the public utility may terminate residential utility service. Except for service diversion or for safety considerations, utility service shall not be disconnected between Thursday at 4:00 p.m. and Monday at 9:00 a.m. or on legal holidays recognized by Utah, or other times the utility's business offices are not open for business. Service may be disconnected only between the hours of 9:00 a.m. and 4:00 p.m.
I. Customer-Requested Termination of Service --
1. A customer shall advise a public utility at least three days in advance of the day on which [
he]the customer wants service disconnected to [his]the customer's residence. The public utility shall disconnect the service within four working days of the requested disconnect date. The customer shall not be liable for the services rendered to or at the address or location after the four days, unless access to the meter has been delayed by the customer.2. A customer who is not an occupant at the residence for which termination of service is requested shall advise the public utility at least 10 days in advance of the day on which [
he]the customer wants service disconnected and sign an affidavit that [he]the customer is not requesting termination of service as a means of evicting [his]the customer's tenants. Alternatively, the customer may sign an affidavit that there are no occupants at the residence for which termination of service is requested and thereupon the disconnection may occur within four days of the requested disconnection date.J. Restrictions Upon Termination of Service Practices -- A public utility shall not use termination of service practices other than those set forth in these rules. A utility shall have the right to use or pursue legal methods to ensure collections of obligations due it.
K. Policy Statement Regarding Elderly and [
Handicapped]Disabled -- The state recognizes that the elderly and [handicapped]disabled may be seriously affected by termination of utility service. In addition, the risk of inappropriate termination of service may be greater for the elderly and [handicapped]disabled due to communication barriers [which]that may exist by reason of age or infirmity. Therefore, this section is specifically intended to prevent inappropriate terminations of service which may be hazardous to these individuals. In particular, Subsection R746-200-7(G), requiring adequate notice of impending terminations of service, including notification to third parties upon the request of the account holder, Subsection R746-200-7(D)(1), restricting termination of service when the termination of service will cause or aggravate a serious illness or infirmity of a person living in the residence, and Subsection R746-200-7(D)(2), restricting terminations of service to residences when life-supporting equipment is in use, are intended to meet the special needs of elderly and [handicapped]disabled persons, as well as those of the public in general.L. Load Limiter as a Substitute for Termination of Service, Electric Utilities --
1. An electric utility may, but only with the customer's consent, install a load limiter as an alternative to terminating electric service for non-payment of a delinquent account or for failure to comply with the terms of a deferred payment agreement or Commission order. Conditions precedent to the termination of electric service must be met before the installation of a load limiter.
2. Disputes about the level of load limitation are subject to the informal review procedure of Subsection R746-200-8.
3. Electric utilities shall submit load limiter policies and procedures to the Commission for their review before the implementation and use of those policies.
R746-200-8. Informal Review.
A. A person who is unable to resolve a dispute with the utility concerning a matter subject to Public Service Commission jurisdiction may obtain informal review of the dispute by a designated employee within the Division of Public Utilities. This employee shall investigate the dispute, try to resolve it, and inform both the utility and the consumer of his findings within five business days from receipt of the informal review request. Upon receipt of a request for informal review, the Division employee shall, within one business day, notify the utility that an informal complaint has been filed. Absent unusual circumstances, the utility shall attempt to resolve the complaint within five business days. In no circumstances shall the utility fail to respond to the informal complaint within five business days. The response shall advise the complainant and the Division employee regarding the results of the utility's investigation and a proposed solution to the dispute or provide a timetable to complete any investigation and propose a solution. The utility shall make reasonable efforts to complete any investigation and resolve the dispute within 30 calendar days. A proposed solution may be that the utility request that the informal complaint be dismissed if, in good faith, it believes the complaint is without merit. The utility shall inform the Division employee of the utility's response to the complaint, the proposed solution and the complainant's acceptance or rejection of the proposed solution and shall keep the Division employee informed as to the progress made with respect to the resolution and final disposition of the informal complaint. If, after 30 calendar days from the receipt of a request for informal review, the Division employee has received no information that the complainant has accepted a proposed solution or otherwise completely resolved the complaint with the utility, the complaint shall be presumed to be unresolved.
B. Mediation -- If the utility or the complainant determines that they cannot resolve the dispute by themselves, either of them may request that the Division attempt to mediate the dispute. When a mediation request is made, the Division employee shall inform the other party within five business days of the mediation request. The other party shall either accept or reject the mediation request within ten business days after the date of the mediation request, and so advise the mediation-requesting party and the Division employee. If mediation is accepted by both parties or the complaint continues to be unresolved 30 calendar days after receipt, the Division employee shall further investigate and evaluate the dispute, considering both the customer's complaint and the utility's response, their past efforts to resolve the dispute, and try to mediate a resolution between the complainant and the utility. Mediation efforts may continue for 30 days or until the Division employee informs the parties that the Division has determined that mediation is not likely to result in a mutually acceptable resolution, whichever is shorter.
C. Division Access to Information During Informal Review or Mediation -- The utility and the complainant shall provide documents, data or other information requested by the Division, to evaluate the complaint, within five business days of the Division's request, if reasonably possible or as expeditiously as possible, if they cannot be provided within five business days.
D. Commission Review -- If the utility has proposed that the complaint be dismissed from informal review for lack of merit and the Division concurs in the disposition, if either party has rejected mediation or if mediation efforts are unsuccessful and the Division has not been able to assist the parties in reaching a mutually accepted resolution of the informal dispute, or the dispute is otherwise unresolved between the parties, the Division in all cases shall inform the complainant of the right to petition the Commission for a review of the dispute, and shall make available to the complainant a standardized complaint form with instructions approved by the Commission. The Division itself may petition the Commission for review of a dispute in any case which the Division determines appropriate. While a complainant is proceeding with an informal or a formal review or mediation by the Division or a Commission review of a dispute, no termination of service shall be permitted, if any amounts not disputed are paid when due, subject to the utility's right to terminate service pursuant to R746-200-7(F), Termination of Service Without Notice.
E. Notwithstanding any other provision of this rule (R746-200-8), a customer who has provided to a public utility a life-supporting equipment statement and who has received the 30-day written notice of proposed termination of service described in R746-200-7.D.2 may bypass informal review and receive an expedited hearing before the Commission if the Commission receives a written complaint and request for a hearing from the customer within 10 calendar days after the date the notice is postmarked.
KEY: public utilities, rules, utility service shutoff
Date of Enactment or Last Substantive Amendment: [
August 22, 2014]2015Notice of Continuation: November 28, 2012
Authorizing, and Implemented or Interpreted Law: 54-4-1; 54-4-7; 54-7-9; 54-7-25
Document Information
- Effective Date:
- 5/22/2015
- Publication Date:
- 04/15/2015
- Type:
- Notices of Proposed Rules
- Filed Date:
- 03/30/2015
- Agencies:
- Public Service Commission, Administration
- Rulemaking Authority:
Section 54-4-1
Section 54-7-9
Section 54-7-25
Section 54-4-7
- Authorized By:
- Jordan White, Legal Counsel
- DAR File No.:
- 39246
- Summary:
- Changing the current process under which a public utility must petition the Public Service Commission for approval to terminate utility service in some instances, this proposed rule change eliminates the requirement for the utility to petition for approval. Instead, the proposed rule change increases the disclosures the public utility is required to include in a notice of proposed termination involving life-supporting equipment (clearly and plainly informing the customer of the customer's ...
- CodeNo:
- R746-200-7
- CodeName:
- {29595|R746-200-7|R746-200-7. Termination of Service}
- Link Address:
- Public Service CommissionAdministrationHEBER M WELLS BLDG160 E 300 SSALT LAKE CITY, UT 84111-2316
- Link Way:
Sheri Bintz, by phone at 801-530-6714, by FAX at 801-530-6796, or by Internet E-mail at sbintz@utah.gov
Jordan White, by phone at 801-530-6712, by FAX at , or by Internet E-mail at jordanwhite@utah.gov
- AdditionalInfo:
- More information about a Notice of Proposed Rule is available online. The Portable Document Format (PDF) version of the Bulletin is the official version. The PDF version of this issue is available at http://www.rules.utah.gov/publicat/bull-pdf/2015/b20150415.pdf. The HTML edition of the Bulletin is a convenience copy. Any discrepancy between the PDF version and HTML version is resolved in favor of the PDF version. Text to be deleted is struck through and surrounded by brackets ([example]). ...
- Related Chapter/Rule NO.: (1)
- R746-200-7. Informal Review.