Filed: 05/02/2013 12:20:31 PMRULE ANALYSIS
Purpose of the rule or reason for the change:
This rule was proposed by the Air Quality Board as part of a package that included six other rule changes. After the public comment period, two of those proposed rules, Section R307-403-2 (DAR No. 37264) and Rule R307-420 (DAR No. 37265), are undergoing substantive changes and cannot be made effective until 07/01/2013. There are no changes being made to the proposed rule; however, in order for this rule to have the same effective date as the two rules that are being changed, the Division of Air Quality is filing a change in proposed rule (CPR) for this rule. (DAR NOTE: The CPR for Section R307-403-2 is under DAR No. 37264 and the CPR for Rule R307-420 is under DAR No. 37265 in this issue, June 1, 2013, of the Bulletin.)
Summary of the rule or change:
There are no changes being made to the proposed rule. This filing is being done so that this rule can be made effective on the same date as Section R307-403-2 (DAR No. 37264) and Rule R307-420 (DAR No. 37265). (DAR NOTE: This CPR has been filed to extend the time frame for the proposed amendment for this rule that was published in the March 1, 2013, issue of the Utah State Bulletin, on page 36.)
State statutory or constitutional authorization for this rule:
- Subsection 19-2-104(3)(q)
- Section 19-2-108
Anticipated cost or savings to:
the state budget:
There are no changes being made; therefore, there are no anticipated costs or savings.
local governments:
There are no changes being made; therefore, there are no anticipated costs or savings.
small businesses:
There are no changes being made; therefore, there are no anticipated costs or savings.
persons other than small businesses, businesses, or local governmental entities:
There are no changes being made; therefore, there are no anticipated costs or savings.
Compliance costs for affected persons:
There are no changes being made; therefore, there are no anticipated compliance costs for affected persons.
Comments by the department head on the fiscal impact the rule may have on businesses:
There are no changes being made; therefore, there will be no fiscal impact on businesses.
Amanda Smith, Executive Director
The full text of this rule may be inspected, during regular business hours, at the Division of Administrative Rules, or at:
Environmental Quality
Air QualityRoom Fourth Floor
195 N 1950 W
SALT LAKE CITY, UT 84116-3085Direct questions regarding this rule to:
- Mark Berger at the above address, by phone at 801-536-4000, by FAX at 801-536-0085, or by Internet E-mail at mberger@utah.gov
Interested persons may present their views on this rule by submitting written comments to the address above no later than 5:00 p.m. on:
This rule may become effective on:
07/01/2013
Authorized by:
Bryce Bird, Director
RULE TEXT
DAR NOTE: No change has been proposed; see the reason under the "Reason for the Change" in the rule analysis above. To view the amended text, see the proposed amendment that was published in the March 1, 2013, issue of the Utah State Bulletin, on page 36.
R307. Environmental Quality, Air Quality.
R307-401. Permit: New and Modified Sources.
[
R307-401-19. Analysis of Alternatives.The owner or operator of a major new source or major modification to be located in a nonattainment or maintenance area or which would impact a nonattainment or maintenance area must, in addition to the requirements in R307-401, submit with the notice of intent an adequate analysis of alternative sites, sizes, production processes, and environmental control techniques for such proposed source which demonstrates that benefits of the proposed source significantly outweigh the environmental and social costs imposed as a result of its location, construction, or modification. The director shall review the analysis. The analysis and the director's comments shall be subject to public comment as required by R307-401-7. The preceding shall also apply in Salt Lake and Davis Counties for new major sources or modifications which are considered major for precursors of ozone, including volatile organic compounds and nitrogen oxides.]KEY: air pollution, permits, approval orders, greenhouse gases
Date of Enactment or Last Substantive Amendment: 2013
Notice of Continuation: June 6, 2012
Authorizing, and Implemented or Interpreted Law: 19-2-104(3)(q); 19-2-108
Document Information
- Effective Date:
- 7/1/2013
- Publication Date:
- 06/01/2013
- Filed Date:
- 05/02/2013
- Agencies:
- Environmental Quality,Air Quality
- Rulemaking Authority:
Subsection 19-2-104(3)(q)
Section 19-2-108
- Authorized By:
- Bryce Bird, Director
- DAR File No.:
- 37268
- Related Chapter/Rule NO.: (1)